Environmental Assessment Act
Section 9
Notice Of Approval To Proceed With The Undertaking

RE:     An Environmental Assessment for the Biggars Lane Landfill Expansion

Proponent:  County of Brant
EA File No.:  03-08-02
EA Reference No.:  14119

Take Notice that the period for requesting that the application or matters related to the application be referred to the Ontario Land Tribunal for a hearing, provided for in the Notice of Completion of the Review for the above-noted undertaking, expired on January 14, 2022. I received no submissions requesting a hearing by the Ontario Land Tribunal before the expiration date.

Having considered the purpose of the Environmental Assessment Act, the approved terms of reference, the environmental assessment, the ministry review of the environmental assessment and submissions received, I hereby give approval to proceed with the undertaking, subject to conditions set out below.

Reasons

My reasons for giving approval are:

  1. The proponent has complied with the requirements of the Environmental Assessment Act.
  2. The environmental assessment has been prepared in accordance with the approved Terms of Reference.
  3. On the basis of the proponent’s environmental assessment and the ministry review, the proponent’s conclusion that the advantages of this undertaking outweigh its disadvantages appears to be valid.
  4. The proponent has demonstrated that the environmental effects of the undertaking can be appropriately prevented, changed, mitigated or remedied.
  5. On the basis of the proponent’s environmental assessment, the ministry review and the conditions of approval, the construction, operation and maintenance of the undertaking will be consistent with the purpose of the Environmental Assessment Act.
  6. The ministry’s review of government agency, public and Indigenous Community comments on the environmental assessment and the ministry review has indicated no outstanding concerns that cannot be addressed through commitments in the environmental assessment, through the conditions set out below or through future approvals that will be required.
  7. I am not aware of any outstanding issues with respect to this undertaking which suggest that a hearing should be required; as such, a hearing is unnecessary and would cause undue delay to the implementation of the undertaking.

Conditions

Approval to proceed with the undertaking is subject to the following conditions:

Dated the 6th day of April 2022 at Toronto.

[Original Signed by]
Minister of the Environment, Conservation and Parks
777 Bay Street, 5th Floor
Toronto ON  M7A 2J3

Approved by O.C. No.
Date O.C. Approved


Order in Council 996/2022