RE: An Environmental Assessment for the Eastern Ontario Waste Handling Facility Expansion

Proponent: GFL Environmental Inc.

EA Reference No.: 15038

EA File No.: 03-08-02

Take notice that the prescribed deadline for requiring a hearing, provided for in the Notice of Completion of the Ministry Review for the above-noted Undertaking, expired on November 9, 2018.

Having considered the purpose of the Environmental Assessment Act, the approved Terms of Reference, the Environmental Assessment, and the Ministry Review and comments received, I hereby give approval to proceed with the Undertaking, subject to the conditions set out below.


Reasons

My reasons for giving approval are:

  1. The Proponent has complied with the requirements of the Environmental Assessment Act.
  2. The Environmental Assessment has been prepared in accordance with the approved Terms of Reference.
  3. On the basis of the Proponent’s Environmental Assessment and the Ministry Review, the Proponent’s conclusion that the advantages of this Undertaking outweigh its disadvantages appears to be valid.
  4. No other beneficial alternative method of implementing the Undertaking was identified.
  5. The Proponent has demonstrated that the environmental effects of the Undertaking can be appropriately managed and mitigated.
  6. On the basis of the Proponent’s Environmental Assessment, the Ministry Review and the conditions of approval, the construction, operation and maintenance of the Undertaking will be consistent with the purpose of the Environmental Assessment Act (Section 2).
  7. The government agency, public and Indigenous community review of the Environmental Assessment has indicated no outstanding concerns that cannot be addressed through commitments made in the Environmental Assessment, through conditions set out below, or through future approvals that will be required. I am not aware of any outstanding issues with respect to this Undertaking which suggest that a hearing should be required.

Conditions

The approval is subject to the following conditions:

  1. Definitions

    For the purposes of these conditions:

    "Construction"
    means physical construction activities, including site preparation works, but does not include the tendering of contracts.
    "Date of Approval”
    means the date on which the Order in Council pertaining to the approval of the Environmental Assessment was signed by the Lieutenant Governor-in-Council.
    “Director”
    means the Director of the Environmental Assessment and Permissions Branch.
    “Environmental Assessment”
    means the document titled Eastern Ontario Waste Handling Facility Landfill Expansion Environmental Assessment, June 2018.
    “Environmental Compliance Approval”
    means an approval issued under Part II.1 of the Environmental Protection Act, R.S.O. 1990, c. E.19, as amended.
    “Ministry”
    means the Ontario Ministry of the Environment, Conservation and Parks.
    “Indigenous Communities”
    means: Mohawk Council of Akwesasne, Algonquins of Ontario Consultation Office, Huron Wendat Nation Council, Métis Nation of Ontario Council, Mohawks of the Bay of Quinte –Tyendinaga Mohawk Council, and, Métis Nation of Ontario Ottawa Region Métis Council
    “Proponent”
    means GFL Environmental Inc., its agents, successors, and assigns.
    “Site”
    means the Eastern Ontario Waste Handling Facility consisting of a 66 hectare waste fill area within a waste disposal site of 189 hectares, located on the western half of Lot 16 and Lots 17 and 18, Concession 10, Township of North Stormont, United Counties of Stormont, Dundas and Glengarry.
    “Species at Risk”
    means the species that are on the Species at Risk in Ontario List provided by Ontario Regulation 230/08 of the Endangered Species Act, S.O. 2007, c. 6 as amended.
    “Undertaking”
    means the planning, design, construction, operation, and closure of the expansion of the waste fill area at the Site for an additional 4,200,000 cubic metres of waste disposal capacity (including cover) and associated works, as specified in the Environmental Assessment.

Dated the 24 day of February 2019 at Toronto.

[Original Signed by]
Minister of the Environment, Conservation and Parks
77 Wellesley Street West
11th Floor, Ferguson Block
Toronto, Ontario
M7A 2T5

Approved by O.C. No. ______
Date O.C. Approved ______


Order in Council 372/2019