Chapter Description

This chapter covers the construction process involved in sealing the new test hole or dewatering well casing into the hole to reduce the risk of surface water, mineralized groundwater, contaminants or other materials moving along the annular space and impairing groundwater.

The annular space sealing requirements in this chapter do not apply to test holes or dewatering wells that are constructed without casing. The requirements listed in this chapter do not apply to shallow works or other exempted wells discussed in Chapter 3: Exemptions: Wells, Activities & Experienced Professionals.

Regulatory Requirements - Annular Space & Sealing

Relevant Sections - The Wells Regulation

The Wells Regulation - Casing – Subsections 13(11.1), 13(13), 13(20)

Annular Space – Sections/Subsections 14, 14.1, 14.1(2), 14.2, 14.2(3), 14.3, 14.3(2), 14.4, 14.4(4), 14.5, 14.5(3), 14.6

The Requirements - Plainly Stated

The Wells Regulation requires or exempts the following regarding the creation and sealing of the annular space for new test hole or dewatering well construction.

Annular
space means an open space between a casing or well screen and the side of a well, and includes space between overlapping casings within the well

Subsurface Movement for New Test Hole and Dewatering Well Construction

The person constructing the well must ensure that any annular space, other than the annular space surrounding the well screen, is sealed to prevent any movement of water, natural gas, contaminants or other materials between subsurface formations or between subsurface formations and the ground surface by means of the annular space.

This requirement does not apply where a person constructing a test hole or dewatering well is not required to create an annular space and where no annular space is created.

When a test hole or dewatering well is constructed with an inner casing and permanent outer casing (double walled casing), different requirements apply. For the annular space sealing requirements for this type of well construction, see “New Test Hole or Dewatering Well Completed with a Permanent Outer Casing – Double Walled Casing” below in this Plainly Stated section.

Sealing Annular Space for New Test Holes and Dewatering Wells

See Table 7-1A and Table 7-1B in this chapter for a summary of the requirements outlined in the Wells Regulation that the person constructing the well must follow when creating and filling the annular space for a new test hole or dewatering well, other than jetted wells or wells constructed by the use of a driven point.

The requirements in Table 7-1A and Table 7-1B do not apply for a test hole or dewatering well that is scheduled to be abandoned not later than 180 days after completion of its structural stage.

New Test Holes and Dewatering Wells Constructed by the Use of a Driven Point

A person constructing a well by the use of a driven point must ensure that any annular space is filled to the ground surface using a method and material approved by the Director (see “Grout Placement – Annular Space for Driven Points” section of this chapter).

New Test Holes and Dewatering Wells Constructed by Jetting

The requirements in Table 7-1A and Table 7-1B do not apply to a new test hole or dewatering well that is constructed by jetting. The annular space sealing requirements in “Subsurface Movement for New Test Hole and Dewatering Well Construction” apply to a new test hole or dewatering well constructed by jetting equipment.

Sealing Annular Spaces between Casings

The person constructing the well must ensure that the annular space between casings of different diameters is sealed with suitable sealant to prevent the entry of surface water or other foreign materials into the well.

New Test Hole or Dewatering Well Completed with a Permanent Outer Casing – Double Walled Casing

Some new test holes and dewatering wells are completed with a casing surrounded by a permanent casing of larger diameter (i.e. a permanent outer casing). The annular space around and between the inner casing(s) and the permanent outer casing for a new well must be sealed, as follows:

  • All construction and sealing requirements for the corresponding well construction method in Table 7-1A and Table 7-1B apply with necessary modifications to the test hole or dewatering well’s annular space on the outside of the outer casing. As a necessary modification, the depth of the annular space must extend from the ground surface to at least the bottom of the permanent outer casing or 6 m (19.7 ft), whichever is less.
  • If any groundwater is entering the annular space between the inner casing(s) and the permanent outer casing, the entire annular space between the casings must be sealed, with necessary modifications, in accordance to the minimum requirements of Table 7-1A and Table 7-1B. This requirement does not apply to a well pit or a test hole or dewatering well constructed by the use of a driven point.
  • In all cases, the annular space between casings of different diameters must be sealed with suitable sealant to prevent the entry of surface water and other foreign materials into the well.

Annular Space below the Permanent Outer Casing

Person Constructing a Well

Although the person constructing a well is not specifically required to seal the casing below the permanent outer casing; the person must do what is necessary as the Ontario Water Resources Act prohibits every person from discharging or causing or permitting the discharge of any material of any kind into any waters that may impair the quality of any waters. This includes prohibiting contaminated groundwater from impairing the quality of other groundwater zones when constructing a well.

Well Owner

Persons using the above professional judgment and the well owner should be aware of the following requirement.

If the test hole or dewatering well acts as a pathway for the movement of:

  • natural gas,
  • contaminants, or
  • other materials

between subsurface formations (including aquifers) or between the ground surface and a subsurface formation and where the movement may impair the quality of any waters, the person abandoning the well, often the well owner, must to do one of the following:

  • take measures to prevent the movement of the above materials and ensure the measures are functional at all times, or
  • immediately abandon the well.

Reminder - See Chapter 16: Abandonment: When to Plug & Seal Test Holes & Dewatering Wells and Chapter 17: Abandonment: How to Plug & Seal Test Holes & Dewatering Wells of this manual for further information on abandonment.

Reminder - See Chapter 8: Multi-level Monitoring Test Holes for best management practices on sealing the annular space around the inner casing below the permanent outer casing.

Exemption - Sealing Casing into Bedrock

If a test hole or dewatering well obtains groundwater from the bedrock, the bottom of the casing is not required to be sealed into the bedrock.

Exemptions - Casing

A new test hole or dewatering well is not required to be cased if:

  • abandonment of the new test hole or dewatering well is scheduled to take place not later than 30 days after completion of the structural stage of the well, and
  • the person constructing the new well covers the upper open end of the well securely in a manner sufficient to prevent the entry of surface water and other foreign materials whenever the well is left unattended.

Reminder - Definitions for sealant, bentonite, watertight, tremie pipe and other relevant terms are provided in Chapter 2: Definitions & Clarifications.

Reminder - Detailed information, other construction requirements and annular space filling requirements for new multi-level monitoring test hole installations are covered in Chapter 8: Multi-level Monitoring Test Holes.

Reminder - For information on exemptions and special cases see the “Annular Space Sealing Exemptions and Special Cases,” section of this chapter.

Reminder - The regulatory exemptions described in the "Plainly Stated" section regarding test holes and dewatering wells allow for well technicians, engineers and geoscientists to use their professional expertise to design and install test holes and dewatering wells on a case by case basis.

Implications for Annular Space Filling

Records of Site Condition Regulation - Monitoring wells as defined under O. Reg. 153/04 that are scheduled to be abandoned not later than 180 days after completion of the structural stage are not exempt from the annular space sealing requirements in Table 7-1A and Table 7-1B. Further details on O. Reg. 153/04 requirements are found in “Test Holes and Dewatering Wells Scheduled to be Abandoned Not Later than 180 Days” in the “Annular Space Sealing Exemptions and Special Cases” section of this chapter.

Table 7-1A: Annular Space and Sealing Requirements and Exemptions
New Drilled and Otherfootnote * Test Holes and Dewatering Wells and Well Pits for Test Holes and Dewatering Wells with Casing Drilled Well or any other Well 6 m (19.7 ft) deep that is not listed on Table 7-1A or B (except jetted wells & wells constructed using driven points) Drilled Well or any other Well < 6 m (19.7 ft) deep that is not listed on Table 7-1A or B (except jetted wells & wells constructed using driven points) New Well Pit (see Chapter 12: Equipment Installation)
Minimum Diameter of Hole Greater Than Outer Casing Diameter to Create Annular Space
  • Minimum Diameter is 7.6 cm (3 inches)
  • Minimum Diameter is 7.6 cm (3 inches)
  • Minimum Diameter is 7.6 cm (3 inches)
Minimum Diameter of Hole Greater Than Outer Casing Diameter to Create Annular Space
  • Minimum Diameter is 5.1 cm (2 inches)
  • If centralizers are attached to casing > 6 m (19.7 ft) below the ground surface using rotary drilling equipment or
  • If breakaway guide is attached 2 m (6.3 ft) above the bottom of any casing using cable tool equipment
  • Minimum Diameter is 5.1 cm (2 inches)
  • If centralizers are attached to casing > 6 m (19.7 ft) below the ground surface using rotary drilling equipment OR
  • If breakaway guide is attached 2 m (6.3 ft) above the bottom of any casing using cable tool equipment
  • Minimum Diameter is 7.6 cm (3 inches)
Minimum Depth of Annular Space below Ground Surface at the Diameter Specified in the Previous Rowfootnote ***
  • 6 m (19.7 ft)
  • Where no well screen is installed:

    • bottom of well
  • If well screen installed:

    • bottom of well screen, and
    • top of well screen must not be closer to ground surface than 2.5 m (8.2 ft)footnote **
  • Bottom of well pit
Bottom of Filter Pack Material around Well Screen if present
  • Bottom of well
  • Bottom of well
  • None
Type of Annular Filter Pack Material around Well Screen
  • Clean, washed gravel or sand placed during or after placement of well screen and casing OR
  • Clean, washed gravel or sand developed after placement of suitable sealant using surging to remove fine grained soils
  • Clean, washed gravel or sand placed during or after placement of well screen and casing OR
  • Clean, washed gravel or sand developed after placement of suitable sealant using surging to remove fine grained soils
  • None
Maximum Top of Annular Filter Pack Material around Well Screen and Well Casing
  • At least the top of well screen but no closer to ground surface than 6 m (19.7 ft)
  • Only applies where well screen is present
  • At least the top of well screen, but no closer to ground surface than 2.5 m (8.2 ft)
  • Only applies where well screen is present
  • None
Annular Seal Material around Casing in remaining Open Annular Space
  • Suitable sealant placed using tremie pipe with bottom end of pipe immersed in rising accumulation of sealant.
  • Sealant particle size must not be subject to bridging for a well that has a minimum hole diameter that is not less than 5.1 cm (2 inches) more than the outer casing diameter. The casing also must be properly aligned in the hole.
  • If no well screen is used, suitable sealant must be used to fill the space from the bottom of the annular space adjacent to the casing up to ground surface.
  • Suitable sealant placed using tremie pipe with bottom end of pipe immersed in rising accumulation of sealant.
  • Sealant particle size must not be subject to bridging for a well that has a minimum hole diameter that is not less than 5.1 cm (2 inches) more than the outer casing diameter. The casing also must be properly aligned in the hole.
  • If no well screen is used, suitable sealant must be used to fill the space from the bottom of the annular space adjacent to the casing up to ground surface.
  • None
Where Cement Is Used in Suitable Sealant Mixture
  • Allow cement to cure to manufacturer’s specifications or for 12 hours whichever is longer. If cement mixture settles, the suitable sealant shall be topped up to the original level
  • Allow cement to cure to manufacturer’s specifications or for 12 hours whichever is longer. If cement mixture settles, the suitable sealant shall be topped up to the original level
  • Allow cement to cure to manufacturer’s specifications or for 12 hours whichever is longer. If cement mixture settles, the suitable sealant shall be topped up to the original level
Table 7-1B: Annular Space and Sealing Requirements and Exemptions
New Bored Test Holes and Dewatering Wells with Concrete Casing and Dug (or Excavated) Test Holes and Dewatering Wells Bored Well with Concrete Casing 6 m (19.7 ft) deep Bored Well with Concrete Casing < 6 m (19.7 ft) deep Dug (or Excavated) Well
Minimum Diameter of Hole Greater than Outer Casing Diameter to Create Annular Space
  • From ground surface to 2.5 m (8.2 ft) below ground surface
  • Minimum Diameter is 15.2 cm (6 inches)
  • From ground surface to 2.5 m (8.2 ft) below ground surface
  • Minimum Diameter is 15.2 cm (6 inches)
  • None
Minimum Diameter of Hole Greater than Outer Casing Diameter to Create Annular Space
  • From 2.5 m (8.2 ft) below the ground surface
  • Minimum Diameter is 7.6 cm (3 inches)
  • From 2.5 m (8.2 ft) below the ground surface
  • Minimum Diameter is 7.6 cm (3 inches)
  • None
Minimum Depth of Annular Space below Ground Surface at the Diameter Specified in the Previous Rowfootnote ***
  • 6 m (19.7 ft)
  • Where no well screen is installed:

    • bottom of well
  • If well screen installed:

    • bottom of well screen, and
    • top of well screen must not be closer to ground surface than 2.5 m (8.2 ft)footnote **
  • None
Bottom of Filter Pack Material around Well Screen if Present
  • Bottom of well screen
  • Bottom of well screen
  • Bottom of well
Type of Annular Filter Pack, Granular or Native Material
  • Clean, washed gravel or sand deposited only after placement of well screen and casing
  • Only applies if well screen is present
  • Clean, washed gravel or sand deposited only after placement of well screen and casing
  • Only applies if well screen is present
  • Clean, washed gravel, or
  • Clean, washed sand, or
  • Native materials (soil) excavated from the well only if they are not from a contaminated area and the major horizons of soil are excavated and stored separately, kept free of contamination and then backfilled within the annular space in the same relative position that the horizon originally occupied.
Maximum Top of Annular Filter Pack Material around Well Screen and Well Casing
  • At least the top of well screen but no closer to ground surface than 6 m (19.7 ft) below ground surface
  • Only applies where well screen is present
  • At least the top of well screen but no closer to ground surface than 2.5 m (8.2 ft) below ground surface
  • Only applies where well screen is present
  • No closer to ground surface than 2.5 m (8.2 ft) below ground surface
Annular Seal Material around Casing in Remaining Open Annular Space from Filter Pack, Granular or Native Material to 2.5 m (8.2 ft) below Ground Surface
  • Suitable sealant placed using tremie pipe with bottom end of pipe immersed in rising accumulation of sealant
  • If no well screen is used, suitable sealant must be used to fill the space from the bottom of the well up to this depth.
  • Suitable sealant placed using tremie pipe with bottom end of pipe immersed in rising accumulation of sealant
  • If no well screen is used, suitable sealant must be used to fill the space from the bottom of the well up to this depth.
  • Suitable sealant that has structural strength to support weight of persons and vehicles
Annular Seal Material around Casing from 2.5 m (8.2 ft) below Ground Surface to Ground Surface
  • Bentonite granules, pellets or chips that have been screened to manufacturer’s specifications and have a diameter range between 6 to 20 mm (0.23 to 0.8″) are placed immediately above the suitable sealant
  • Bentonite granules, pellets or chips that have been screened to manufacturer’s specifications and have a diameter range between 6 to 20 mm (0.23 to 0.8″) are placed immediately above the suitable sealant
  • Suitable sealant that has structural strength to support weight of persons and vehicles
Where Cement is Used in Suitable Sealant Mixture
  • Allow cement to cure to manufacturer’s specifications or for 12 hours whichever is longer. If cement mixture settles, the suitable sealant shall be topped up to the original level
  • Allow cement to cure to manufacturer’s specifications or for 12 hours whichever is longer. If cement mixture settles, the suitable sealant shall be topped up to the original level
  • Allow cement to cure to manufacturer’s specifications or for 12 hours whichever is longer. If cement mixture settles, the suitable sealant shall be topped up to the original level

Reminder - When mixing, handling or placing any grout material (wet or dry) it is important to always follow manufacturer’s specifications and recommended procedures. It is also important to consult the Material Safety Data Sheet (MSDS) for additional information on safe handling and usage.

Definition - A tremie pipe is a pipe or tube with an inner diameter that is at least three times the diameter of the largest particle of material to pass through it and that is used to conduct material to the bottom of a hole, including a hole containing standing water. For clarification with respect to a tremie pipe, a pipe or tube means a long, hollow (empty space) cylinder.

Relevant Sections - Additional Regulations or Legislation

Ontario Water Resources Act, R.S.O. 1990, chapter O 40. subsection 30(1)

Ontario Regulation 153/04 (Records of Site Condition) as amended made under Environmental Protection Act, R.S.O. 1990, chapter E. 17

Relevant Standards

ASTM D 5092-04 – Standard Practice for Design and Installation of Ground Water Monitoring Wells. DOI: 10.1520/D5092-04E0footnote 1.

ASTM D 6724-04 – Standard Guide for Selection and Installation of Direct-Push Ground Water Monitoring Wells. DOI: 10.1520/D6724-04footnote 1.

ASTM D 6725-04 – Standard Practice for Direct-Push Installation of Pre-pack Screen Monitoring Wells in Unconsolidated Aquifers. DOI: 10.1520/D6725-04footnote 1

Key Concepts

What to Consider When Sealing the Annular Space

The Annular Space

During construction of a well, an annular space is created when the size of the hole in the ground is larger than the casing and well screen diameter.

Best Management Practice – Annular Space Diameter

An annular space needs to be large enough to ensure sealant will fill and adhere around the entire test hole or dewatering well casing. In most subsurface conditions, the hole diameter should be 102 mm to 203 mm (4 inches to 8 inches) larger than the outer finished casing diameter because it facilitates the use of a tremie pipe and the placement of the sealant, and possibly the filter pack, in the annular space.

Best Management Practice – Annular Space Depth

A properly sealed annular space running the entire length of the casing stabilizes and improves the overall integrity of the test hole or dewatering well.

Purpose of the Seal

If a casing is placed into the ground without an annular space, the formation material along the casing becomes loosened and disturbed. The disturbed section along the casing can become a pathway for the migration of contaminants, gas and groundwater.

A properly created and filled annular space around a casing will:

  • isolate a discrete zone,
  • prevent migration of surface water and other foreign materials into the well and aquifers,
  • prevent migration of groundwater or contaminants between water bearing formations and subsurface formations,
  • prevent migration of groundwater or contaminants between water bearing formations and the ground surface,
  • prevent aquifer depressurization by stopping the upward migration of water along the casing, or
  • prevent gas migration.

Examples of Improperly Sealed Annular Space

Figure 7-1: Visible Open Annular Space Adjacent to a Test Hole

See text below for description.

Figure 7-1 shows a white plastic well casing of a test hole extending out of the ground surface. An open space adjacent to the casing (i.e., annular space) is visible at the ground surface and extends to the bottom of the casing (not visible in photograph). The ground surface also slopes towards the well. Any surface water or other foreign materials can flow along the ground surface towards the well and discharge into the open space beside the well casing. The open space acts as a direct pathway for foreign materials to enter and impair groundwater resources and creates quality assurance problems with samples.

Figure 7-2: Visible Open Annular Space Below Pitless Adapter and Horizontal Waterline to the Bottom of the Casing

See text below for description.

Figure 7-2 shows a visible open space (i.e., annular space) below the pitless adapter and horizontal waterline. The open space extends to the bottom of the casing (not shown in photograph). Above the waterline, the person constructing the well installed a bluish-grey coloured bentonite grout in the annular space from above the pitless adapter to the ground surface (within blue oval dotted line). When the area beside the well was excavated, it became evident that the annular space was improperly filled (or left open) below the pitless adapter until the exterior of the well was excavated. The open space acts as a direct pathway for foreign materials to enter and impair groundwater resources.

Annular Space Sealing Exemptions and Special Cases

The Ontario Water Resources Act prohibits any person from impairing the quality of any waters in Ontario. This section describes regulatory exemptions to the annular space sealing requirements listed in Table 7-1A and Table 7-1B for test holes and dewatering wells.

These annular space sealing exemptions do not release anyone from complying with the Ontario Water Resources Act general provision regarding the impairment of waters.

The exemptions discussed in this section are: uncased wells, shallow works, wells shallower than 2.5 m with well screens, test holes and dewatering wells scheduled to be abandoned not later than 180 days and new test hole or dewatering well completed with a permanent outer casing - double walled casing.

Uncased Wells

The Wells Regulation - Where a test hole or dewatering well needs to be constructed without casing (and thus no annular space) for testing or dewatering purposes, wells must be scheduled to be abandoned not later than 30 days after completion of the well’s structural stage, and the person constructing the well must cover the upper open end of the well securely in a manner sufficient to prevent the entry of surface water and other foreign materials whenever the well is left unattended during the 30 day (or less) period.

An example for an uncased well could include an open test pit that is considered a test hole and is not an exempted well (e.g., trench, ditch). In this case, it may not be appropriate to insert well casing and seal an annular space to allow for the person to:

  • make appropriate field observations of formations in the case of a test hole, or
  • lower the water table around an excavation in the case of a dewatering well.

These excavations can be properly filled after observations or dewatering has been completed.

Reminder - Further information, including best management practices, and examples of uncased test holes is found in the “Exemption from the Requirement to Case the Test Hole or Dewatering Well” section of Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well.

Shallow Works

If a test hole or dewatering well is no more than 3.0 m (9.8 ft) deep, the shallow works exemption and requirements can apply to the construction, maintenance and abandonment of the well as long as the well:

  • is not constructed in a contaminated area,
  • does not penetrate through an entire formation that is not an aquifer, and
  • is not constructed in an area known for flowing wells.

Reminder - For further information on shallow works please refer to Chapter 3: Exemptions: Wells, Activities & Experienced Professionals.

Best Management Practice – Sealing Annular Space of Shallow Works

The Ontario Water Resources Act prohibits the impairment of the quality of any waters. As such, shallow works with casing should have a properly sized annular space around the casing and have the annular space properly filled with an appropriate sealing material. Sealing the well casing to the formation prevents the side of the well from acting as a pathway for foreign materials to enter and impair groundwater resources, and prevents quality assurance problems.

Definition - A shallow works is a test hole or dewatering well that is made to a depth of not more than 3.0 m (10 ft) below the ground surface and that meets the other conditions described in Chapter 3: Exemptions: Wells, Activities & Experienced Professionals.

Records of Site Condition Regulation - Starting on July 1, 2011, O. Reg. 153/04 prescribes that the provisions of the Ontario Water Resources Act and of Regulation 903 of the Revised Regulations of Ontario, 1990 (Wells) made under that Act, that would apply to a test hole but for section 1.1, and subsections 13 (2), 14.1 (2), 14.2 (3), 14.3 (2), 14.4 (4) and 14.5 (3) of that regulation, apply to a monitoring well installed for the purpose of,

  1. a phase one environmental site assessment; and
  2. a phase two environmental site assessment.

Implications for the Qualified Person

The qualified person shall ensure that phase one and phase two environmental site assessments (ESAs) are conducted in accordance with the requirements stated above.

Implications for Annular Space Size and Filling for New Test Holes

The above requirement means that, if a new test hole qualifies as a shallow works and is to be used as a monitoring well in an ESA for a record of site condition, then:

  • the annular space size and filling exemptions for a test hole under shallow works do not apply, and
  • the annular space size and filling requirements for a test hole stated in Table 7-1A and Table 7-1B and the “Plainly Stated” section do apply.

Reminder - The above requirement in O. Reg. 153/04 also affects obligations relating to casing material, well screen material and shallow works for monitoring wells. See Chapter 3: Exemptions: Wells, Activities & Experienced Professionals and Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well for further information.

Records of Site Condition Regulation - Please refer to O. Reg. 153/04 for RSC requirements.

Reminder - For clarification on the term “monitoring well” and “qualified person” in the Records of Site Condition regulation see Chapter 2: Definitions & Clarifications, Table 2-2.

Wells Shallower Than 2.5 Metres with Well Screens

The person constructing the well must ensure that the top of the gravel or sand material placed in the annular space to at least the top of the well screen is no closer than 2.5 metres to the ground surface for many new wells. Where a new test hole that is less than 2.5 m (8.2 ft) deep and a well screen is needed, the well must be:

  • constructed by digging or by the use of a driven or jetted point,
  • scheduled to be abandoned not later than 180 days after completion of the structural stage of the test hole or dewatering well, or
  • constructed with a casing surrounded by a larger permanent outer casing (sometimes referred to as a double walled casing).

The depth requirement for the top of the sand and gravel layer does not apply to shallow works.

Reminder - For further information on the minimum depth of a test hole and dewatering well with and without a well screen, see the “Minimum Depth of Annular Space below Ground Surface” row in Table 7-1A and Table 7-1B and the “Plainly Stated” section of Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well.

Test Holes and Dewatering Wells Scheduled to be Abandoned Not Later Than 180 Days

The Wells Regulation - A person constructing a test hole or dewatering well that is scheduled to be abandoned not later than 180 days after the completion of its structural stage must seal any annular space, other than annular space surrounding the well screen, to prevent any movement of water, natural gas, contaminants or other material between subsurface formations or between subsurface formations and the ground surface.

The methods to create and seal an annular space specified in the Wells Regulation and Table 7-1 A and Table 7-1 B to achieve a proper seal are not mandatory, but would be a good practice. This allows well technicians, engineers and geoscientists to use their professional expertise to design and install test holes and dewatering wells on a case by case basis, thereby enabling the testing, sampling or dewatering of various groundwater intervals.

This annular space requirement does not apply where a person constructing a test hole or dewatering well is not required to create an annular space and where no annular space is created.

When a test hole or dewatering well is constructed with an inner casing and permanent outer casing (double walled casing), different requirements apply. The specific requirements for this type of construction are found in the “New Test Hole or Dewatering Well Completed with a Permanent Outer Casing – Double Walled Casing” section below.

Best Management Practice – Sealing the Annular Space to Prevent Movement

Persons constructing test holes or dewatering wells that are scheduled to be abandoned not later than 180 days after completion of their structural stage should consider following the requirements in Table 7-1A and Table 7-1B.

Best Management Practice – Obtaining Written Contracts for Wells Scheduled to be Abandoned

The person constructing a test hole or dewatering well should have a signed written contract with the well purchaser and, if not the same, the land owner, that indicates the well owner(s) has agreed to abandon the well in accordance with the Wells Regulation not later than 180 days after the completion of the structural stage of the test hole or dewatering well. The written contract will help protect the interests of the person constructing the well if the completed test hole or dewatering well is not abandoned within 180 days and the contract will advise the well owner(s) of this scheduling requirement.

Records of Site Condition Regulation - Starting on July 1, 2011, O. Reg. 153/04 prescribes that the provisions of the Ontario Water Resources Act and of Regulation 903 of the Revised Regulations of Ontario, 1990 (Wells) made under that Act, that would apply to a test hole but for section 1.1, and subsections 13 (2), 14.1 (2), 14.2 (3), 14.3 (2), 14.4 (4) and 14.5 (3) of that regulation, apply to a monitoring well installed for the purpose of,

  1. a phase one environmental site assessment; and
  2. a phase two environmental site assessment.

Implications for the Qualified Person

The qualified person shall ensure that phase one and phase two environmental site assessments (ESAs) are conducted in accordance with the requirements stated above.

Implications for Annular Space Size and Filling for New Test Holes

With respect to annular space size and filling, the above requirement in O. Reg. 153/04 means that, if a new test hole is constructed, is scheduled to be abandoned not later than 180 days after the completion of its structural stage, and is to be used as a monitoring well in an ESA for a record of site condition, then:

  • the annular space size and filling exemptions for a test hole stated in this section do not apply, and
  • the annular space size and filling requirements for a test hole stated in Table 7-1A and Table 7-1B and the “Plainly Stated” section do apply.

Reminder - The above requirement in O. Reg. 153/04 also affects obligations relating to casing material, well screen material and shallow works for monitoring wells. See Chapter 3: Exemptions: Wells, Activities & Experienced Professionals and Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well for further information.

Records of Site Condition Regulation - Please refer to O. Reg. 153/04 for RSC requirements.

Reminder - For clarification on the term “monitoring well” and “qualified person” in the Records of Site Condition regulation see Chapter 2: Definitions & Clarifications, Table 2-2.

Wells Shallower Than 2.5 Metres with Well Screens

The person constructing the well must ensure that the top of the gravel or sand material placed in the annular space to at least the top of the well screen is no closer than 2.5 metres to the ground surface for many new wells. Where a new test hole that is less than 2.5 m (8.2 ft) deep and a well screen is needed, the well must be:

  • constructed by digging or by the use of a driven or jetted point,
  • scheduled to be abandoned not later than 180 days after completion of the structural stage of the test hole or dewatering well, or
  • constructed with a casing surrounded by a larger permanent outer casing (sometimes referred to as a double walled casing).

The depth requirement for the top of the sand and gravel layer does not apply to shallow works.

Reminder - For further information on the minimum depth of a test hole and dewatering well with and without a well screen, see the “Minimum Depth of Annular Space below Ground Surface” row in Table 7-1A and Table 7-1B and the “Plainly Stated” section of Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well.

Test Holes and Dewatering Wells Scheduled to be Abandoned Not Later Than 180 Days

The Wells Regulation - A person constructing a test hole or dewatering well that is scheduled to be abandoned not later than 180 days after the completion of its structural stage must seal any annular space, other than annular space surrounding the well screen, to prevent any movement of water, natural gas, contaminants or other material between subsurface formations or between subsurface formations and the ground surface.

The methods to create and seal an annular space specified in the Wells Regulation and Table 7-1 A and Table 7-1 B to achieve a proper seal are not mandatory, but would be a good practice. This allows well technicians, engineers and geoscientists to use their professional expertise to design and install test holes and dewatering wells on a case by case basis, thereby enabling the testing, sampling or dewatering of various groundwater intervals.

This annular space requirement does not apply where a person constructing a test hole or dewatering well is not required to create an annular space and where no annular space is created.

When a test hole or dewatering well is constructed with an inner casing and permanent outer casing (double walled casing), different requirements apply. The specific requirements for this type of construction are found in the “New Test Hole or Dewatering Well Completed with a Permanent Outer Casing – Double Walled Casing” section below.

Best Management Practice – Sealing the Annular Space to Prevent Movement

Persons constructing test holes or dewatering wells that are scheduled to be abandoned not later than 180 days after completion of their structural stage should consider following the requirements in Table 7-1A and Table 7-1B.

Best Management Practice – Obtaining Written Contracts for Wells Scheduled to be Abandoned

The person constructing a test hole or dewatering well should have a signed written contract with the well purchaser and, if not the same, the land owner, that indicates the well owner(s) has agreed to abandon the well in accordance with the Wells Regulation not later than 180 days after the completion of the structural stage of the test hole or dewatering well. The written contract will help protect the interests of the person constructing the well if the completed test hole or dewatering well is not abandoned within 180 days and the contract will advise the well owner(s) of this scheduling requirement.

Records of Site Condition Regulation - The person constructing a test hole or dewatering well should have a signed written contract with the well purchaser and, if not the same, the land owner, that indicates the well owner(s) has agreed to abandon the well in accordance with the Wells Regulation not later than 180 days after the completion of the structural stage of the test hole or dewatering well. The written contract will help protect the interests of the person constructing the well if the completed test hole or dewatering well is not abandoned within 180 days and the contract will advise the well owner(s) of this scheduling requirement.

  1. a phase one environmental site assessment; and
  2. a phase two environmental site assessment.

Implications for the Qualified Person

The qualified person shall ensure that phase one and phase two environmental site assessments (ESAs) are conducted in accordance with the requirements stated above.

Implications for Annular Space Size and Filling for New Test Holes

With respect to annular space size and filling, the above requirement in O. Reg. 153/04 means that, if a new test hole is constructed, is scheduled to be abandoned not later than 180 days after the completion of its structural stage, and is to be used as a monitoring well in an ESA for a record of site condition, then:

  • the annular space size and filling exemptions for a test hole stated in this section do not apply, and
  • the annular space size and filling requirements for a test hole stated in Table 7-1A and Table 7-1B and the “Plainly Stated” section do apply.

Reminder - The above requirement in O. Reg. 153/04 also affects obligations such as casing material, well screen material and shallow works for monitoring wells. See Chapter 3: Exemptions: Wells, Activities & Experienced Professionals and Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well for further information.

Records of Site Condition Regulation - Please refer to O. Reg. 153/04 for RSC requirements.

New Test Holes or Dewatering Well Completed with a Permanent Outer Casing - Double Walled Casing

In some cases, multiple casings of different diameters are installed in new wells to reach a groundwater zone. This type of installation is common in multi-level monitoring test holes and flowing wells. The annular space around and between the inner casing(s) and the permanent outer casing for a new well that will be in operation for more than 180 days must be sealed as follows:

  • All construction and sealing requirements for the corresponding well construction method in Table 7-1A and Table 7-1B apply with necessary modifications to the test hole or dewatering well’s annular space on the outside of the outer casing. As a necessary modification, the depth of the annular space must extend from the ground surface to at least the bottom of the permanent outer casing or 6 m (19.7 ft), whichever is less.
  • If any groundwater is entering the annular space between the inner casing(s) and the permanent outer casing, the entire annular space between the casings must be sealed, with necessary modifications, in accordance to the minimum requirements of Table 7-1A and Table 7-1B. This requirement does not apply to a well pit or to a test hole or dewatering well constructed by the use of a driven point.
  • In all cases, the annular space between casings of different diameters must be sealed with suitable sealant to prevent the entry of surface water and other foreign materials into the well.

Although the person constructing a well is not specifically required to seal the casing below the permanent outer casing; the person must do what is necessary as the Ontario Water Resources Act prohibits every person from discharging or causing or permitting the discharge of any material of any kind into any waters that may impair the quality of any waters. This includes prohibiting contaminated groundwater from impairing the quality of other groundwater zones when constructing a well.

Persons using the above professional judgement and the well owner should be aware of the following requirement.

The Wells Regulation - If a test hole or dewatering well acts as a pathway for the movement of:

  • natural gas,
  • contaminants, or
  • other material

between subsurface formations (including aquifers) or between the ground surface and a subsurface formation and where the movement may impair the quality of any waters, the person abandoning the well, often the well owner, must do one of the following:

  • take measures to prevent the movement and ensure the measures are functional at all times, or
  • immediately abandon the well.

Reminder - See Chapter 16: Abandonment: When to Plug & Seal Test Holes & Dewatering Wells and Chapter 17: Abandonment: How to Plug & Seal Test Holes & Dewatering Wells of this manual for further information on well abandonment.

Reminder - See Chapter 8: Multi-level Monitoring Test Holes for best management practices on sealing the annular space around the inner casing below the permanent outer casing.

Reminder - Detailed information, other construction requirements and annular space sealing requirements and best management practices for new multi-level monitoring test hole installations are covered in Chapter 8: Multi-Level Monitoring Test Holes.

Requirements for Sealing Various Types of Cased Test Holes or Dewatering Wells

Figures 7-3 to 7-9 show cross sectional illustrations and relevant graphics for the construction of various new test holes or dewatering wells. The figures show the Wells Regulation requirements for minimum hole size, annular space filling products around well screens and suitable sealant in the annular space around the casings.

Reminder - The requirements shown in Figures 7-3 to 7-9 do not apply to test holes and dewatering wells that are scheduled for abandonment (plugged and sealed) not later than 180 days after completion of the well’s structural stage.

Reminder - All figures and diagrams are for illustrative purposes only and do not necessarily represent full compliance with other requirements found in the Wells Regulation (e.g., well covering during construction).

Reminder - During and after construction the person constructing the test hole or dewatering well must ensure surface drainage is such that water will not collect or pond in the vicinity of the well.

Reminder - The person constructing the test hole or dewatering well must also cover the upper open end of the well securely to prevent entry of surface water and other foreign materials into the well during well construction.

Reminder - For details on the hole, casing and other construction requirements not shown in Figure 7-3 to Figure 7-9 refer to the following chapters in this manual:

  • Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well, and
  • Chapter 9: Completing the Test Hole or Dewatering Well Structure.

Reminder - Each of the test holes or dewatering wells shown in Figures 7-3 to 7-9 may encounter conditions that may require specialized design or construction. For example:

  • flowing artesian conditions,
  • presence of gas, or
  • breathing (sucking and blowing) conditions where the well and aquifer formation are significantly affected by the changes in atmospheric pressure.

Therefore the illustrations and graphics may not depict every circumstance.

Figure 7-3: Examples Of Wells Constructed By Drilling Or Direct Push Without Using A Driven Point (Not Scheduled To Be Abandoned Within 180 Days After Completing Structural Stage)

Please see the descriptive text below

Figure 7-3 shows a cross-sectional diagram of three drilled wells (A, B and C) placed into the subsurface. The subsurface consists of a clay deposit underlain by a sand deposit. The sand deposit is underlain by a clay deposit. The clay deposit is underlain by a gravel deposit. The gravel deposit is underlain by a limestone bedrock with water bearing fractures.

The well on the left of the diagram is example “A”. The well is completed with a casing that extends vertically from above the ground surface through the clay and into the sand overburden. A well screen is attached to the bottom of the casing. A plug is attached to the bottom of the well screen. A filter pack has been placed around the well screen to the side of the hole. A secondary filter pack has been placed on top of the filer pack. The top of the secondary filter pack extends just above the sand deposit. Suitable sealant has been placed in the annular space above the secondary filter pack. A vermin-proof well cap has been affixed to the top of the casing. The ground surface has been mounded around the casing to prevent surface water from ponding beside the well.

The well in the middle of the diagram is example “B”. The well is completed with a casing that extends vertically from above the ground surface to the gravel deposit. A well screen is attached to the bottom of the casing. A plug is attached to the bottom of the well screen. A filter pack has been placed around the well screen to the side of the hole. A secondary filter pack has been placed on top of the fitler pack. The top of the secondary filter pack extends just above the gravel deposit. Suitable sealant has been placed in the annular space above the secondary filter pack. A vermin-proof well cap has been affixed to the top of the casing. The ground surface has been mounded around the casing to prevent surface water from ponding beside the well.

The well on the right side of the diagram is example “C”. The well is completed with a casing that extends vertically from above the ground surface through overburden to the limestone bedrock. As a best management practice (BMP), centralizers have been placed from the outside of the casing to the side of the hole to centre the casing in the hole. A well screen is attached to the bottom of the casing and is located at the water bearing zone in the bedrock. A plug is attached to the bottom of the well screen. A filter pack has been placed around the well screen to the side of the hole. A secondary filter pack has been placed on top of the filter pack. The top of the secondary filter pack is located in the bedrock. Suitable sealant has been placed in the annular space above the secondary filter pack. A vermin-proof well cap has been affixed to the top of the casing. The ground surface has been mounded around the casing to prevent surface water from ponding beside the well.

Note 1 states BMP = Best management practice

Note 2 states the top of the filter pack around the well screen must be no closer than 2.5 metres (8.2 feet) below the ground surface.

Note 3 states the hole diameter must be at least 7.6 centimetres (3 inches) greater than the final outer casing (see A or B) for at least 6 metres (19.7 feet) from the ground surface or the full depth of the well (whichever is less).

Note 4 states the hole must be large enough to allow for the installation of a tremie pipe in the annular space. The tremie pipe must be immersed in the rising accumulation of sealant in the annular space.

Reminder - See the “Filter Packs around Well Screens for Drilled Test Holes or Dewatering Wells” section in Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well for filter pack material information and best management practices about filter packs.

Reminder - If centralizers are used with rotary equipment or a breakaway guide is used with cable tool equipment, the hole diameter must be at least 5.1 cm (2 inches) greater than the final outer casing (see C) for at least 6 m (19.7 ft) from the ground surface or the full depth of the well (whichever is less). For additional information, see the “Centering the Casing” section in Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only, and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Figure 7-4: Example Of Multi-Cased Bedrock Well Constructed By Drilling Or Direct Push Without Using A Driven Point (Not Scheduled To Be Abandoned Within 180 Days After Completing Structural Stage)

Please see the descriptive text below

Figure 7-4 shows a cross-sectional diagram of multi-cased bedrock well placed into the subsurface. The subsurface consists of a silt deposit underlain by a clay deposit. The clay deposit is underlain by sandstone bedrock. The sandstone is underlain by a limestone bedrock with water bearing fractures.

The well is completed with an inner casing that extends vertically from above the ground surface through overburden to the limestone bedrock. The joints between the sections of inner casing have been made watertight. An outer casing has been placed in the well that extends vertically from above the ground surface through overburden to the sandstone bedrock. A drive shoe has been placed on the outer casing. As a best management practice (BMP), centralizers have been placed from the outside of the outer casing to the side of the hole to centre the outer casing in the hole. As a best management practice (BMP), centralizers have been placed from the outside of the inner casing to the side of the outer casing to centre the inner casing in the hole. A well screen is attached to the bottom of the inner casing and is located at the water bearing zone in the bedrock. A plug is attached to the bottom of the well screen. A filter pack has been placed around the well screen to the side of the hole. A secondary filter pack has been placed on top of the filter pack. The top of the secondary filter pack is located in the bedrock. Suitable sealant has been placed in the annular space above the secondary filter pack around the inner casing and around the outer casing. A vermin-proof well cap has been affixed to the top of the casing. The ground surface has been mounded around the casing to prevent surface water from ponding beside the well.

Note 1 states BMP = Best management practice

Note 2 states See Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well for information on the hole diameter.

Note 3 states the annular space around the permanent outer casing must be filled with suitable sealant as described in Chapter 7: Annular Space & Sealing. The annular space between the casings must be sealed as described in Chapter 7. As a best management practice, the annular space below the permanent outer casing should be filled as described in the best management practice in this chapter, Chapter 7 and, if applicable, Chapter 8: Multi-level Monitoring Test Holes.

Reminder - See the “Filter Packs around Well Screens for Drilled Test Holes or Dewatering Wells,” section in Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well for filter pack material information and best management practices about filter packs.

Reminder - The sealing requirements found in Table 7-1A and Table 7-1B apply with necessary modifications to the well’s annular space between the casings. This requirement applies if any groundwater is leaking into the annular space between the casings. In all cases, the annular space between casings of different diameters must be sealed with suitable sealant to prevent the entry of surface water and other foreign materials into the well.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only, and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Figure 7-5: Examples Of Directional Well Constructed By Drilling Or Direct Push Without Using A Driven Point (Not Scheduled To Be Abandoned Within 180 Days After Completing Structural Stage)

Please see the descriptive text below

Figure 7-5 shows a cross-sectional diagram of two drilled wells (A and b) placed into the subsurface.

The well on the left of the diagram is example “A”. The well is completed with a casing that extends at a 45 degree angle downward from left to right into the subsurface. The joints between the sections of inner casing have been made watertight. A well screen is attached to the bottom of the casing. The casing and well screen are adjacent to the left side of the hole. A filter pack has been placed around the well screen to the side of the hole. A secondary filter pack has been placed on top of the filer pack. The top of the secondary filter pack extends just above the sand deposit. Suitable sealant has been placed in the annular space above the secondary filter pack and where the casing and well screen are not against the side of the hole. An air tight locking cap (e.g., J-plug) has been affixed to the top of the casing and a well tag has been affixed to the casing. The ground surface has been mounded around the casing to prevent surface water from ponding beside the well.

The well in the right of the diagram is example “B”. The well is completed with a casing that extends at a 45 degree angle downward from left to right into the subsurface. The sections of the casing have been attached to one another with watertight joints. A well screen is attached to the bottom of the casing. Centralizers have been placed on the casing to centre the casing and well screen in the hole. A filter pack has been placed around the well screen to the side of the hole. A secondary filter pack has been placed on top of the filer pack. The top of the secondary filter pack extends just above the sand deposit. Suitable sealant has been placed in the annular space above the secondary filter pack. An air tight locking cap (e.g., J-plug) has been affixed to the top of the casing and a well tag has been affixed to the casing. The ground surface has been mounded around the casing to prevent surface water from ponding beside the well.

Note 1 states BMP = Best management practice

Note 2 states it is important to use centralizers to centre the casing into the hole (see B). A centred casing allows for the proper distribution of filter pack around the well screen and sealant around the casing. The absence of centralizers forces the casing and well screen to move to one side of the hole (see A). This prevents the installation of filter pack around the well screen and the even placement of sealant around the casing. This can allow formation materials to plug the well screen and increases the risk of contaminant and foreign material migration along the side of the casing.

Note 3 states the top of the filter pack around the well screen must be no closer than 2.5 metres (8.2 feet) below the ground surface.

Note 4 states the hole diameter must be at least 7.6 centimetres (3 inches) greater than the final outer casing (see A or B) for at least 6 metres (19.7 feet) from the ground surface or the full depth of the well (whichever is less).

Note 5 states the hole must be large enough to allow for the installation of a tremie pipe in the annular space.

Reminder - See the “Filter Packs around Well Screens for Drilled Test Holes or Dewatering Wells,” section in Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well for filter pack material information and best management practices about filter packs.

Reminder - If centralizers are used with rotary equipment or a breakaway guide is used with cable tool equipment, the hole diameter must be at least 5.1 cm (2 inches) greater than the final outer casing for at least 6 m (19.7 ft) from the ground surface or the full depth of the well (whichever is less). For additional information, see the “Centering the Casing” section in Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Figure 7-6: Drilled Well In Overburden - Natural Development, Casing Pulled Back Exposing Screen Method (Not Scheduled To Be Abandoned Within 180 Days After Completing Structural Stage)

Please see the descriptive text below

Figure 7-6 shows a cross-sectional diagram of a drilled well in the overburden using natural development, casing pulled back method.

The diagram shows a hole extending vertically into an overburden subsurface. A casing extends from above the ground surface into the hole. The annular space between the outside of the casing and the side of the hole is filled with suitable sealant. A well screen is shown within the bottom of the casing and extends out of the bottom of the casing into the bottom of the hole in the subsurface. The well screen is located in a water bearing sand and gravel. The well screen is made up of a K packer, riser pipe, screen, coupling and plug. The K-packer is located at the top of the well screen and seals the inner casing and to the outside of the well screen. The riser pipe extends from the K-packer to below the bottom of the casing in the subsurface. The screen is located below the riser pipe in the subsurface. The coupling and plug are located below the screen.

Note 1 states the hole diameter must be at least 7.6 cm (3 inches) greater than the final outer casing for at least 6 metres (19.7 feet) from the ground surface or the full depth of the well (whichever is less).

Note 2 states if centralizers are used with rotary equipment or a breakaway guide is used with cable tool equipment the hole diameter must be at least 5.1 cm (2 inches) greater than the final outer casing for at least 6 m (19.7 ft) from the ground surface or the full depth of the well (whichever is less).

Reminder - For additional information, see the “Centering the Casing” section in Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well.

Reminder - See Figure 6-17 of Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well that shows how the well’s casing was pulled back and the annular space was created.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Figure 7-7: Example Of Dug Test Hole (Not Scheduled To Be Abandoned Within 180 Days After Completing Structural Stage)

Please see the descriptive text below

Figure 7-7 shows a cross-sectional diagram of a dug well placed a sand deposit.

The dug well consists of a large open hole. A layer of filter pack has been placed at the bottom of the hole. A casing extends vertically from above the ground surface to the filter pack. The joints between the sections of casing have been made watertight. A well screen is attached to the bottom of the casing. A plug is attached to the bottom of the well screen. A filter pack has been placed around the well screen to the side of the hole. As a best management practice, a secondary filter pack has been placed on top of the filer pack. The top of the secondary filter pack extends above the top of the well screen. Suitable sealant has been placed in the annular space above the secondary filter pack. A solid watertight well cover (e.g., J-plug) has been affixed to the top of the casing. The ground surface has been mounded around the casing to prevent surface water from ponding beside the well.

Note 1 states best management practice.

Note 2 states the top of the sand, gravel, or native materials around well screen and casing must not be closer than 2.5 m (8.2 ft) below the ground surface.

Note 3 states the suitable sealant must be able to provide the sufficient structural strength to support the weight of persons and vehicles that may move over the area.

Reminder - The filling material around and above the well screen must be clean washed gravel or sand. Native materials can also be used in the annular space instead of sand or gravel if the well is not constructed in a contaminated area and the materials are excavated separately, stored separately, kept free from contamination and backfilled in the same relative position they originally occupied. See the “Filter Packs around Well Screens for Drilled Test Hole or Dewatering Wells” section and the best management practices about filter pack in Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Figure 7-8: Example Of Dewatering Well Constructed By Jetting With The Use Of A Driven Point (Not Scheduled To Be Abandoned Within 180 Days After Completing Structural Stage)

Please see the descriptive text below

Figure 7-8 shows a cross-sectional diagram of a dewatering well constructed by jetting.

The diagram shows the casing extending from above the ground surface into the subsurface. The casing is high enough to permit the attachment of a well tag. The joints between the sections of casing have been made watertight. A well screen is attached to the bottom of the casing. A driven point has been attached to the bottom of the well screen. A horizontal dotted line above the well screen represents the water table. Suitable sealant has been placed in the irregular annular space above the well screen. A vermin proof well cap has been affixed to the top of the casing. The top of the casing is high enough to permit the attachment of a well tag. The ground surface has been mounded around the casing to prevent surface water from ponding beside the well.

Note 1 states in this example, the hole is constructed by a jetting tool. After the hole is completed, a drive point well screen with casing is placed into the hole. The person constructing the well by jetting must ensure that any annular space around the well casing is sealed to prevent any movement of water, natural gas, contaminants, or other materials between subsurface formations (e.g., aquifers) or between a subsurface formation and the ground surface.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Figure 7-9: Example Of Dewatering Well Constructed By Direct Push Equipment Using A Driven Point (Not Scheduled To Be Abandoned Within 180 Days After Completing Structural Stage)

Please see the descriptive text below

Figure 7-9 shows a cross-sectional diagram of a dewatering well constructed by direct push using a driven point.

The diagram shows a casing that extends from above the ground surface into the subsurface. The casing is high enough to permit the attachment of a well tag. The joints between the sections of casing have been made watertight. A prepacked well screen is attached to the bottom of the casing. A plug is located at the bottom of the well screen. Suitable sealant has been placed in the irregular annular space above the well screen. An expendable driven point is located below the well screen and plug. A horizontal dotted line above the well screen represents the water table.

Another horizontal dotted line with the text: A – A’, is shown extending through the prepacked well screen.

To the right of the cross sectional diagram there is another diagram that states “Cross-section A – A’”. This diagram shows a circle that represents a stainless steel mesh or “v-wire”. Within the mesh/v-wire is slotted well screen tube. Filter material (typically silica sand) is located between the well screen tube and the mesh/v-wire. A horizontal dotted line with the text: A – A’, is shown extending through the mesh/v-wire, filter material and well screen tube.

Note 1 states in this example, drive rod with a detachable (expendable) driven point were driven into the ground. A prepacked well screen with casing was installed into the drive rods. An annular space was created between the drive rods and the casing. The annular space was filled with suitable sealant and the drive rods were removed.

Note 2 states since a driven point was used during the construction, materials and methods approved by the director must be used to fill the annular space.

Since a driven point was used in the construction, materials and methods approved by the Director must be used to fill the annular space.

Reminder - For information about Director’s approval for sealing methods see the: “Grout Placement – Annular Space for Driven Points” section of this chapter.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Comparison Of Bentonite And Cement Grouts

The most common materials used to seal annular spaces are bentonite and neat cement products. Each has specific, unique and desirable properties. Table 7-2 summarizes the advantages and disadvantages of bentonite based sealants (grouts) versus cement based sealants (grouts).

Table 7-2: Some General Bentonite and Cement Advantages and Disadvantagesfootnote 2
Sealants Advantages Disadvantages
Bentonite Based Sealants
  • Suitable low permeability with high solids by weight grouts.
  • Generally non-shrinking and self-healing.
  • No heat generated during hydration.
  • Low density.
  • Sodium bentonite products expand to about 12 to 15 times their original dry volume requiring less material.
  • Short curing time required before proceeding with further well construction. To achieve full gel strength bentonite takes 8 to 48 hours.
  • Properties such as density can be altered with additives.
  • Mineralized groundwater (e.g., >5,000 mg/L of total dissolved solids or >8,000 mg/L chlorides) will inhibit the hydration process and its effectiveness as a sealant. This includes source water used in mixing bentonite for a grout.
  • Groundwater characteristics, such as excess hardness (i.e., >500ppm total hardness) or chlorides (i.e., >1500ppm) may make bentonite an inappropriate choice as a sealant for the environment as it may not set properly.footnote 3
  • High concentrations of organic acids, basic and neutral polar and non-polar organic compounds and neutral non polar organic compounds may cause the hydraulic conductivity of the bentonite to significantly increase and reduce its effectiveness as a sealant.
  • Non Aqueous Phase Liquids (NAPLs) in a subsurface formation, will prevent bentonite from forming an effective seal because the bentonite will shrink and crack.
  • Flowing well environments will likely diminish its effectiveness because it does not have the necessary weight and gel strength to overcome the water pressure.
  • When filling the annular space, bentonite grouts can leak out into open fractures in bedrock environments.
  • May have an impact on the groundwater chemistry and the well components because it can trade off cations such as sodium, aluminum, iron and manganese with them.
  • Additives that may be added to the bentonite slurry (organic and inorganic polymers) may affect groundwater chemistry near the well.
  • Bentonite slurry can make its way through the filter pack(s) and screen(s) into the well and into water samples. Thus, it should be placed no closer than 0.9 m to 1.5 m (3 ft to 5 ft) above the top of a well screen.
  • High solids bentonite are not suitable for use at the surface in arid climates due to potential for dehydration causing cracking and thus, will not perform as a long-term effective sealant.
  • For some grout mixtures with significantly high bentonite solids content (>35%), premature swelling and high viscosity can result in difficult pumping through grout pumps and tremie pipes.
Cement Based Sealants
  • Suitable low permeability.
  • Easily mixed and pumped.
  • Hard-positive seal provides structural integrity (good gel strength) and will not erode or wash-out with water movement.
  • Support and adheres to casing.
  • Any remaining casing is rendered permanent and immovable.
  • Adheres well to bedrock.
  • Properties can be altered with additives to reduce hydration time (calcium chloride), to make sealant stronger (aluminum powder), or have a higher resistance to sulphate rich environments (fly ash).
  • Expanding cements, Types K, M and S, have characteristics and shrinkage-compensating additives that work well as annular seals for monitoring wells.
  • Air-entrained cements work well in cold weather climates because cement with air-entraining agents has water tightness and freeze-thaw resistance.
  • Provide weight and strength to overcome pressures associated with flowing wells.
  • Possible shrinkage if extra water is used, if improper additives are used or if the person is not using shrinkage compensated cements.
  • Settling problems occur if not properly mixed or placed.
  • Long curing time (minimum 12 hours) increases time to complete well and install equipment in well.
  • Produces high heat levels during hydration process that can distort some plastic casings. The high heat of hydration in combination with weight of grout also increases the potential for plastic casing to distort or collapse.
  • High density results in loss of grout to some overburden and bedrock formations.
  • If prompt equipment clean-up does not occur, solidified cement may result in equipment damage.
  • In order to properly set, mixing water needs to be cool, clean, fresh water free of oil soluble chemicals, organic material, alkalies, sulphates and other contaminants.
  • In order to properly set, mixing water needs to have a total dissolved solids concentration of less than 500 mg/L.
  • Using water that has a high pH may increase setting time.
  • Equipment such as a tremie pipe needs to be kept cool to prevent flash set problems to pumps and tremie pipes.
  • If too much water is used in the mixture, the extra water cannot chemically bind with cement (called bleed water), becomes highly alkaline and then can percolate through cement, bentonite and filter pack material causing contamination in groundwater. Voids in the cement created by this bleed water can also be subject to chemical attack and thus, will not perform as a long-term effective sealing material.
  • Prolonged mixing can interrupt heat of hydration process and reduces strength and cement quality.
  • Neat cement mixtures increase the pH in the subsurface formations. An increase in pH can cause dissolved metals to precipitate from solution onto well components like the well screen, and can cause a bias in groundwater sample analyses compared to actual ambient groundwater concentrations.
  • Weight of cement may increase hydraulic pressure on filter pack and thus compromise and permanently plug the pack material and well screen.
  • Too thin of a cement mixture may also allow cement to penetrate, compromise and permanently plug the pack material and well screen.

Notes For Table 7-2:

Reminder - Suitable sealant must be compatible with the quality of the water found in the well. Suitable sealant must be used to seal the annular space of a new test hole or dewatering well that will be in operation for more than 180 days or between casings of a new well.

Reminder - Sealant must be a bentonite mixture of clean water and at least 20% solids by weight or a product that will be equivalent with respect to the ability to form a permanent watertight barrier. For example, a mixture of water with cement, concrete or cement with no more than 5% bentonite solids by weight may be an equivalent sealant in some environments.

Reminder - When evaluating bentonite as a suitable sealant to fill an annular space, the following should be considered:

  • the position of the static water level and its seasonal fluctuations,
  • the ambient groundwater and mixing water quality, and
  • the types and potential concentrations of contaminants (i.e., NAPLs) expected to be encountered.

In some cases three to 8% of bentonite is used as an additive to cement or concrete to improve the workability, slurry weight and density of the cement slurry. This may make it easier to pump or pour the material down a narrow tremie pipe or space. However, bentonite is chemically incompatible with cement and will not swell when mixed with cement. The bentonite additive also reduces the set strength of the seal and lengthens set timefootnote 4.

Reminder - Definitions for sealant, bentonite, watertight, tremie pipe and other relevant terms are provided in Chapter 2: Definitions & Clarifications.

Dry Bentonite Products

Bentonite is manufactured in various forms such as powder, granules, pellets and chips. In some cases, bentonite granules, pellets or chips can be used as a suitable sealant to fill the well’s annular space. See the “Grout Placement – Pouring Bentonite Chips and Pellets from Surface” section of this chapter for further information on the placement of dry bentonite into a well’s annular space. Table 7-3 provides information on the forms of manufactured bentonite.

Table 7-3: Bentonite Grout Products
Product Description Typical Size Hydration Characteristics
Powder
  • Pulverized sodium montmorillonite clay
  • Passes 200 mesh
  • Mixed with water to form a grout that quickly hydrates
  • Should not be poured or dropped dry through a column of standing water
Granules
  • Irregularly shaped sodium montmorillonite clay particles
  • Angular to sub-angular
  • 1.6 mm to 6 mm (116 inch to ¼ inch)
  • Hydrates slower than powder but faster than pellets
  • Should not be poured or dropped dry through a column of standing water
  • Has a tendency to bridge
Pellets
  • Uniformly shaped and sized compressed sodium montmorillonite clay particles
  • Can be coated with a food-grade wax to slow hydration
  • 6 mm to 19 mm (¼ inch to ¾ inch)
  • Hydrates slower than granules but faster than chips
  • Coated pellets hydrate slowly and therefore, can be poured or dropped dry through a column of standing water up to 46 m (150 ft)
Chips
  • Irregularly shaped chunks of sodium montmorillonite clay
  • 6 mm to 19 mm (¼ inch to ¾ inch)
  • Due to high moisture content, chips hydrate slowly
  • Chips can be poured or dropped dry through a column of standing water up to 152 m (500 ft)

Reminder - Some literature indicates that coated bentonite pellets hydrate more slowly than bentonite chips. Other literature indicates that bentonite chips hydrate more slowly than coated bentonite pellets. A person using a bentonite product should always follow the manufacturer’s specifications for the use and placement of the bentonite product.

Calculating Amount Of Materials Required

Before beginning well construction, the amount of materials (sand, gravel and bentonite and/or cement) required to properly seal the annular space should be calculated. Regardless of the base materials or type of grout, it is the measured amount of water and the consistent use of that ratio of water to the dry product that is the key element to achieving the appropriate grout properties.

The amount of material needed will depend on the volume of annular space that needs to be filled (i.e. width and depth of the annular space).

Some things to remember when calculating the amount of materials required:

  • The person constructing the test hole or dewatering well should allow for possible hole increases due to drilling actions, geology and flushing media. Adding 10% to 15% more material to the calculated amount should be considered.
  • The volume of the hole that the casing will occupy should be accounted for.

The following formulae can be used to calculate the volume of the annular space.

Method 1

Annular Space Volume = Volume Of Hole − Volume of Casing, Where:

Volume of Hole = 3.14 × (Diameter of Hole ⁄ 2)2 × Depth
And
Volume of Casing = 3.14 × (Outer Diameter of Casing ⁄ 2)2 × Depth

Or

Volume of Hole = 0.785 × Diameter2 × Depth of Hole
And
Volume of Casing = 0.785 × Outer Diameter of Casing2 × Depth of Hole

Method 2

This is an illustration showing where to measure the diameter of hole, outer diameter of casing and the depth.

Where:

Dh
Diameter of Hole (mm or inches)
dc
Outer diameter of casing (e.g. pipe)(mm or inches)

{[Dh(mm)2 − dc(mm)2] ⁄ 1273} × Depth (metres) = Annular Space Volume (Litres)

Or

{[Dh(inches)2 − dc(inches)2] ⁄ 29.45} × Depth (feet) = Annular Space Volume (Imperial Gallons)

Reminder - The exact amount of grout (sealant) required cannot always be determined due to irregularities in the size of the hole and losses into fractured rock. Extra material should be available on site to add to the initial estimate if needed.

Reminder - See the “Tools for Annular Space and Sealing” section of this chapter for a grouts (sealants) application matrix to help calculate the amount of grout required to fill the annular space.

The following tables can be used to calculate the volume of sealant (i.e., bentonite, cement, concrete) yielded per bag of product.

Table 7-4: Calculating the Volume of Bentonite at 15%, 20% and 23% Solids Based on one 23 kg (50 lbs) Bag of Sodium Bentonite
Volume 15% Solids Grout 20% Solids Grout 23% Solids Grout
Water – Litres 125 91 76
Water – Imperial Gallons 28 20 17
Yield Volume – Litres 133.6 99.6 84.4
Yield Volume – Imperial Gallons 29.4 21.9 18.6

Remidner - The volumes are calculated using the instructions and information on the package or provided by the manufacturer. Different percentages of bentonite slurry are used for various applications when drilling or sealing.

Table 7-5: Calculating the Volume of Concrete and Cement Based on one 43 kg (94 lbs) Bag of Portland Cement
Volume Concrete Portland Cement
Water – Litres 19.7 19.7
Water – Imperial Gallons 4.3 4.3
Yield Volume – Litres 60.3 33.3
Yield Volume – Imperial Gallons 13.3 7.3

Reminder - Table 7-5 is based on one, 43 kilogram (94 pound) bag of cement. The volume of concrete is based on one, 43 kilogram (94 pound) bag of cement mixed with 0.027 cubic metres (1 cubic foot) of sand or gravel. The volumes are calculated by using the instructions and information on the package or directly from the manufacturer.

Reminder - One litre of water weighs one kilogram and Portland cement produces a slurry weight of 1.87 kg/L. The volumes are calculated using the instructions and information on the package or provided by the manufacturer.

Mixing Bentonite Grout (Sealant)

When mixing grout, it is important to follow the manufacturer’s specifications provided on the packaging or with the product.

Inhibited bentonite grouts are a powdered type material that are designed to slow the rate of hydration just long enough to allow the bentonite to be placed into the annular space.

Best Management Practice – Mixing and Placing Bentonite Grout

When mixing bentonite material with clean water, it is important to use a high shear paddle mixer in a mixing drum to thoroughly shearfootnote 5 the bentonite particles to suspension. Once properly mixed, the bentonite grout (sealant) is pumped through a tremie pipe to fill the annular space.

Positive displacement pumps with minimal shearing action are needed when placing bentonite grout (sealant) in the annular space. This technique allows for proper placement and hydration of the bentonite grout (sealant) in the annular space.

Techniques For Successful Mixing

To ensure that the bentonite sealant will last the life of the test hole or dewatering well, bentonite must be mixed with clean water. “Clean,” in this context, means water that will not interfere with the reaction to make a bentonite slurry as recommended by the manufacturer and will not impair the water in and around the well.

Best Management Practice – Techniques for Successful Mixing of Bentonite Grout (Sealant)

The following should be considered when mixing bentonite grouts:

  • Potable water sources (municipal water, etc.) should not be assumed to be acceptable mixing water for bentonite drilling mud or sealant. Mixing water should always be tested for pH, hardness, total dissolved solids and chlorides before mixing. If available, water quality reports can be reviewed in place of testing the mixing water.
  • Bentonite should be mixed with clean water until suspension is achieved. The material should then be immediately pumped into the annular space through a tremie pipe.
  • Small batches should be prepared to ensure that at a mixture of least 20% bentonite solids by weight is maintained.
  • Gear pumps are better suited for bentonite sealants consisting of bentonite polymer and water mixtures (two step grouts).
  • Progressing cavity pumps are better suited for bentonite sealants consisting of bentonite and water mixtures (one step grouts).

Consequences Of Poorly Mixed Bentonite Grout

Mixing water that is not clean (e.g., highly mineralized water), may inhibit the hydration process of the bentonite grout and its effectiveness as a sealant.

If excess “hardness” is present in the mixing water, the polymers and/or bentonite may clump and adhere to the paddles during the mixing phase. In severe cases it can result in plugging of tremie lines and disruption of the grouting process.

Grout that is mixed or sheared too much will start to hydrate too rapidly. This will result in difficulty pumping the grout, plugging up of the tremie line, and wasting a batch.

Reminder - The person constructing the well should follow the manufacturer’s specifications for pH, hardness, chloride, total dissolved solids and other water quality issues (see Table 7-2 for further information on water chemistry and its potential effect on bentonite).

Mixing Cement or Concrete Grout (Sealant)

Cement grout (sealant) must be made using carefully measured quantities of water and Portland cement (see Table 7-5). In concrete grout, aggregate and other materials (e.g., plasticizers) are added to cement and water. For more information on cement, see How Cement is Made.

A paddle mixer in a mixing drum with either a progressive cavity or gear pump is a common choice for mixing and pumping cement or concrete grout (sealant). Small portable grouting machines that combine both the mixing and the pumping operations are also often used. These machines typically have a positive displacement pump because it can work efficiently against much greater head pressures with low loss of grout volume.

Techniques For Successful Mixingfootnote 6

Best Management Practice – Techniques for Successful Mixing of Cement or Concrete Grout (Sealant)

The following should be considered when mixing cement or concrete grouts:

  • The mixing water needs to be cool, clean, fresh water free of oil soluble chemicals, organic material, alkalies and other contaminants and have a total dissolved solids concentration of less than 500 mg/Lfootnote 7 to ensure proper setting of the grout (sealant).
  • It is important to mix the grout thoroughly and ensure it is free of lumps.
  • If the mixture is purchased from a ready–mix concrete plant, the correct proportions of cement, water and other aggregate material, if present, should be verified by using equipment such as a drilling fluid balance.
  • It is important to use a protective strainer on the tank from which the grout is pumped into the well’s annular space through a tremie pipe.
  • The material should be immediately pumped into the annular space through a tremie pipe.

Consequences Of Poorly Mixed Cement Grout

Mixing water that is has a high pH or high level of total dissolved solids may result in increased setting times (i.e. slow hydration) and/or failure to set. See Table 7-2 for further information on water chemistry and its potential affect on cement.

If the grout is not thoroughly mixed and free of lumps then partial setting may occur and the effectiveness of the seal will be compromised.

Premature setting may occur due to an incorrect estimate of the hole temperature, the use of hot mixing water, improper water to cement ratios, contaminants in the mixing water, mechanical failures, and interruptions to pumping operations.

Improper water to cement ratios may also cause excessive shrinkage of the grout.

Grout Placement Requirements

The Wells Regulation has specific requirements for the placement of materials in the annular space for new cased test holes and dewatering wells that are not scheduled to be abandoned within 180 days of completion (see Table 7-1A and Table 7-1B in “Plainly Stated”).

The Wells Regulation requires that any annular space of any new cased well, other than the annular space surrounding the well screen, must be sealed to prevent any movement of water, natural gas, contaminants or other material between subsurface formations or between subsurface formations and the ground surface by means of the annular space. This requirement does not apply to the annular space around an inner casing where a new well has been constructed with a permanent outer casing (see the “New Test Hole or Dewatering Well Completed with a Permanent Outer Casing – Double Walled Casing” section of this chapter).

For new cased test holes and dewatering wells, the Wells Regulation requires that

  • a tremie pipe be used to install the suitable sealant.
  • the bottom of the tremie pipe remain immersed in the rising accumulation of sea

This tremie pipe requirement does not apply for new dug wells, wells constructed with the use of a driven point, wells constructed by jetting and to test holes and dewatering wells that are scheduled to be abandoned within 180 days of completion.

Successful placement of the grout will depend on the temperature, stability, size of the annular space and pressure in the hole, and how well the casing is centered. The following best management practice on sealing the annular space provides suggestions to help achieve a successful seal.

Best Management Practice – Sealing the Annular Space

The following will help ensure that the sealant will provide a satisfactory seal:

  • During placement of sealant, the sealant returning to the surface should be the same consistency as the sealant that is being pumped.
  • The first indication of sealant returning to surface is not an indication to stop pumping.
  • Where the tremie pipe is placed in the annular space, active pumping of the sealant should continue as the tremie pipe is extracted from the annular space to ensure effective displacement.
  • Sealant pump suction and discharge hoses should be adequately sized to overcome friction losses and decrease chances of plugging.
  • Suction and discharge hose connections to the pump should be made using quick-connect style couplings. This will save time when attempting to locate a blockage in the hose and allow faster cleanup.
  • When the pump is also used for mixing, the discharge hose should be plumbed in such a manner to allow changeover from mixing to pumping sealant without shutting down the pump.
  • A pressure gauge should be installed on the pump discharge and monitored to ensure that the working pressure does not exceed the hose and pipe maximum pressure rating. A sudden increase in pressure may indicate that the tremie pipe has become plugged.

Sealant (Grout) Placement Techniques

The following sections provide different techniques used to place suitable sealant into an annular space. The Wells Regulation requirements found in the following sections do not apply to test holes or dewatering wells that are scheduled to be abandoned within 180 days of completion of the well’s structural stage.

Group Placement - Inner String Method

In the inner string method of placing grout, the tremie pipe is suspended in the casing. A cementing (float) shoe is attached to the bottom of the casing before the casing is placed in the hole. The tremie pipe is lowered until it engages the shoe.

Placing Grout Using the Inner String Method

To place grout using the inner string method:

  1. A float shoe or other similar device is attached to the bottom of the casing before the casing is placed in the hole.
  2. The casing is placed in the hole to the bottom of the well. Then the tremie pipe is lowered inside the casing until it engages the shoe. This permits the grout to pass into the annular space but prevents it from leaking back into the casing while pumping the grout.
  3. Water or drilling fluid is placed into the casing to prevent the grout from coming back up the casing.

Reminder - For shorter strings of casing [i.e., 6 to 30 metres (20 ft to 100 ft)], the tremie pipe is sealed at the top of the casing using one or two stacked top well seals. The barrier created by the well seals along with the weight of the drilling fluid or water will minimize the amount of grout that can travel back up the inside of the casing string during and after the pumping process.

  1. The grout is pumped through the tremie pipe and float shoe and is forced upward around the casing.
  2. The tremie pipe is disconnected and removed.
  3. All grouting equipment is cleaned.
    1. Where bentonite grout is used and before further well construction proceeds, the bentonite should be allowed time to achieve gel strength. Bentonite takes 8 to 48 hours to achieve full gel strength.

    Best Management Practice – Topping Up Settled Bentonite Grout

    The bentonite grout should be topped up to the original level before drilling continues if there has been settling or subsidence in the annular space.

    1. Where cement grout is used, cement must be allowed to set according to manufacturer’s specifications, or 12 hours, whichever is longer. If there has been settling or subsidence in the annular space, the cement grout must be topped up to the original level before drilling continues.
  4. The float shoe or other device is drilled out or removed from the bottom of the casing.

Reminder - The sealant at the bottom of the casing is susceptible to damage when drilling restarts. The sealant must be physically and structurally sound and capable of withstanding the initial pressures of drilling. After the placement of grout, it is important to prevent flushing media from pushing up and exerting pressure on the grout column when drilling resumes. This upward pressure can be caused by the displacement of water in the casing when using percussion drilling action or when using air or water based flushing media.

Figure 7-10: Pumping Grout (Sealant) Using The Inner String Method

See text below for description.

Figure 7-10 shows a steel casing extending out of the ground behind a drill rig. A clamp has been placed around the casing and above a wooden stump to hold the casing in place. A hose from a grout pump (not shown) is attached to a tremie line above the well casing and hidden behind a steel plate. A bentonite grout (suitable sealant) is being forced down the tremie pipe inside the well casing. The grout is being pushed out below the casing and is being forced up the annular space. The benontite grout is seen coming out of the annular space onto the ground surface around the casing.

Figure 7-11: Inner String Method Of Grout Placement

See text below for description.

Figure 7-11 shows a cross-sectional diagram of the inner string method to place grout (sealant) into a well.

Figure 7-11 shows a cross-sectional diagram of the inner string method to place grout (sealant) into a well.

The diagram shows a vertical hole that extends into the subsurface. A suspended casing has been placed into the hole from above the ground surface to just above the bottom of the hole. A float shoe has been installed at the bottom portion of the casing. A tremie pipe is inserted within the casing and through the float shoe. Centralizers have been installed between the outside of the tremie pipe and the inside of the casing.

An annular space is located between the outside of the casing to the side of the hole. Above the ground surface, a horizontal tremie pipe is attached to the vertical tremie pipe. The horizontal tremie pipe is attached to a grout pump. Another horizontal pipe is attached to the grout pump and a vertical pipe. The vertical pipe is attached to a hopper that contains sealant.

There are arrows and small circles in the diagram demonstrating the flow of sealant through the hopper, horizontal tremie pipe, grout pump and vertical tremie pipe and discharging out of the bottom of the tremie pipe into the bottom of the hole. The arrows are also demonstrating the sealant is being forced upward in the annular space from the bottom of the hole to the ground surface.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only, and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Grout Placement - Tremie Pipe Outside Casing Method

When using this placement method, the grout material is pumped or placed using a tremie pipe that is installed in the annular space.

Best Management Practice – Using a Grout Pump

When a grout pump is used with a tremie pipe, any fluid (i.e., drilling mud or water) of lesser weight than the grout will be displaced from the annular space. This technique assists in the proper filling of any voids or spaces with grout (sealant).

Best Management Practice – Using a Larger Diameter Tremie Pipe

The use of a larger diameter tremie pipe:

  • reduces the amount of friction loss that is associated with a small diameter tremie pipe,
  • reduces the velocity of grout entering the annular space,
  • enhances the efficiency of the displacement process, and
  • significantly improves the effectiveness of the overall seal.

Reminder - The annular space must meet regulatory requirements (see Table 6-2 of Chapter 6: Constructing the Hole, Casing & Covering the Well and Table 7-1A and Table 7-1B in this chapter) and be large enough to accommodate the tremie pipe (see Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well; “Best Management Practice - Size of Test Hole or Dewatering Well”).

Placing Grout Using the Outside Casing Method

To place grout using the tremie pipe outside the casing:

  1. The lower end of the casing is closed with a drillable plug to ensure the grout that is placed in the annular space cannot enter the casing.
    Another option is to drive the casing into the undisturbed formation below the hole.
  2. The tremie pipe is installed into the annular space. The person constructing the well must ensure that the tremie pipe reaches the bottom of the annular space.
    1. If a pump is used, the grout is pumped down the tremie pipe discharging into the bottom annular space. Continued discharge of grout into the bottom of the annular space causes the rising accumulation of grout to reach the ground surface.

      The pump must be capable of developing enough pressure to overcome the friction caused by moving the grout through the tremie pipe and up the annular space.

      Issues with a grout pressure head that may prevent the upward placement of grout with a pump are not usually a concern since the grout that is rising to the ground surface is at or below the grout pump elevation.

      In some circumstances, it may be advisable to pull the tremie pipe up at about the same rate that grout is filling the annular space after the first mixed batch of grout is pumped into the annular space. This will minimize the grout pressure head on the tremie pipe outlet and reduce any chances of the tremie pipe being stuck in the hole due to hydration of the grout.

    2. If a pump is not used, the grout is poured down a tremie pipe above the ground surface. The grout flows from the tremie pipe into the bottom of the annular space by the force of gravity. The tremie pipe is raised slowly and the bottom of the tremie pipe remains in the rising accumulation of the grout until the grout reaches the ground surface.

      The bottom of the tremie pipe must remain submerged in the rising accumulation of grout until placement of the grout is complete.

  3. Grouting may be complete when the grout leaving the annular space at the ground surface is of the same consistency as the grout being introduced into the bottom of the annular space.
  4. The tremie pipe is disconnected and removed.
  5. All grouting equipment is cleaned.
    1. Where bentonite grout is used and before further well construction proceeds, the bentonite should be allowed time to achieve gel strength. Bentonite takes 8 to 48 hours to achieve full gel strength.

    Best Management Practice – Topping Up Settled Bentonite Grout

    The bentonite grout should be topped up to the original level before drilling continues if there has been settling or subsidence in the annular space.

    1. Where cement grout is used, cement must be allowed to set according to manufacturer’s specifications, or 12 hours, whichever is longer. If there has been settling or subsidence in the annular space, the cement grout must be topped up to the original level before drilling continues.
  6. The plug is drilled out or removed from the bottom of the casing.

Reminder - The sealant at the bottom of the casing is susceptible to damage when drilling restarts. The sealant must be physically and structurally sound and capable of withstanding the initial pressures of drilling. After the placement of grout, it is important to prevent flushing media from pushing up and exerting pressure on the grout column when drilling resumes. This upward pressure can be caused by the displacement of water in the casing when using percussion drilling action or when using air or water based flushing media.

Figure 7-12: Outside Casing Method Of Grout Placement

See text below for description.

Figure 7-12 shows a cross-sectional diagram of the outside casing method to place grout (sealant) into a well.

Figure 7-12 shows a cross-sectional diagram of the outside casing method to place grout (sealant) into a well.

The diagram shows a vertical hole that extends into the subsurface. A suspended casing has been placed into the hole from above the ground surface to just above the bottom of the hole. A plug has been placed at the bottom of the casing. An annular space is located from the outside of the casing to the side of the hole. A vertical tremie pipe has been installed inside the annular space, located to the left of the casing, from above the ground surface to the bottom of the casing.

Above the ground surface, a horizontal tremie pipe is attached to the vertical tremie pipe. The horizontal tremie pipe is attached to a grout pump. Another horizontal pipe is attached to the grout pump and a vertical pipe. The vertical pipe is attached to a hopper that contains sealant.

There are arrows and small circles in the diagram demonstrating the flow of sealant through the hopper, horizontal tremie pipe, grout pump and vertical tremie pipe and discharging out of the bottom of the tremie pipe into the bottom of the hole. The arrows are also demonstrating the sealant is being forced upward in the annular space from the bottom of the hole to the ground surface.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only, and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Figure 7-13: Installing Tremie Pipe Outside Casing

See text below for description.

Figure 7-13 shows a tremie pipe being installed in the annular space of a drilled well. The permanent steel casing is being held in place by the drilling rig. A larger diameter starter (or temporary) casing has been installed during the drilling of the hole. The difference in diameter between the two casings has created an annular space large enough to allow for the placement of the tremie pipe.

Figure 7-14: Tremie Pipe Remains In Hole During Grout Placement

See text below for description.

Figure 7-14 shows the tremie pipe remaining in the annular space while grout is being pumped through it to fill the entire annular space. In some cases, the tremie pipe may need to be raised during pumping to ensure the tremie pipe does not get stuck in the curing sealant.

Figure 7-15: A Successful Seal

See text below for description.

Figure 7-15 shows a suitable sealant that has been placed in the annular space along the casing and up to the ground surface.

Figure 7-16: Example Of A Properly Sealed Annular Space

See text below for description.

Figure 7-16 shows a hole excavated beside a drilled well. The photograph shows the bluish-grey coloured bentonite grout that has filled the annular space of the drilled well adjacent to the black drilled well casing. The bentonite has also adhered to the sand and gravel overburden. The pop can adjacent to the casing near the bottom of the excavation provides the approximate thickness of the grout.

Figure 7-17: Example Of A Properly Sealed Annular Space - Close Up

See text below for description.

Figure 7-17 shows a close-up of the same drilled well. The photograph shows the bluish-grey bentonite grout that has filled the annular space of the well adjacent to the black drilled well casing and which has adhered to the sand and gravel overburden.

Grout Placement - Pouring Without Tremie Pipe

A tremie pipe is not required when filling the annular space of:

  • a new dug well,
  • the upper 2.5 m (8.2 ft) of a new bored well with approved concrete casing, or
  • a new well pit.

The Wells Regulation - The grout (sealant) must provide appropriate structural strength to support the weight of persons and vehicles that may move over the filled annular space of a new dug well or well pit.

Reminder - Care is needed when filling the annular space around a large diameter casing that is thin-walled (e.g., fibreglass or corrugated steel), to reduce the risk of distorting the casing wall or casing joints. Care is also needed when pouring suitable sealant to ensure that bridging will not occur.

Grout Placement - Pouring Bentonite Chips And Pellets From Surface

A dry, manufactured bentonite product, such as chips and pellets, can be placed into the hole’s annular space by a gravity method (i.e. pouring the material from the ground surface) where there is a larger diameter starter (or temporary) casing surrounding a smaller diameter permanent casing. In this case, the starter (or temporary) casing is a pipe that acts as a tremie pipe.

Tremie Pipe
A pipe or tube with an inner diameter that is at least three times the diameter of the largest particle of material to pass through it, and that is used to conduct material to the bottom of a hole, including a hole containing standing water.

In this case, the annular space between the starter casing and permanent outer casing must meet the definition of a tremie pipe for this method to be used.

Upon proper placement of the dry bentonite product into the annular space, the starter (or temporary) casing is removed.

If this method of placement of dry bentonite is used, certain precautions should be taken for the reasons discussed below. When pouring dry bentonite from the surface, there is an increased risk of bridging. A high rate of pouring causes the bentonite to clog at an elevation above the bottom of the annular space. In other cases, the bentonite encounters groundwater and hydrates before it settles to the bottom of the annular space. Open gaps, due to bridging, can allow contaminants to travel vertically in the open portion of the well, destabilize the structure of the well and decrease the effectiveness of the plugging materials.

This method may also lead to uneven hydration of dry bentonite in certain situations. As such, improperly hydrated bentonite may not hold the weight of the well column and may cause serious structural problems with the well.

See the best management practice titled "Taking Precautions when Using and Pouring Dry Bentonite Products" in this chapter.

Best Management Practice – Taking Precautions when Using and Pouring Dry Bentonite Products

If sodium bentonite is used and poured in an annular space from the surface using a starter casing or other tremie pipe, the material should be in a pellet or chip form. The material should be screened and placed in accordance with the manufacturer’s specifications.

Precautions when plugging a well with dry bentonite products include the following:

  • Installing a considerably larger diameter hole than the casing and the casing has been centered using centralizers.
  • Pouring the products at a rate no faster than 3 minutes per 22 kilogram (50 pound) bag.
  • Halting the pouring process occasionally and lowering a weighted measuring tape into the well until it reaches the top of the products to confirm that bridging has not occurred.
  • Using a tamping device to break any bridges that form.
  • Lifting the starter casing as the dry material is added in a manner that keeps the bottom of the tremie pipe immersed in the rising accumulation of dry material, in order to reduce the risk of void spaces between the bentonite and the formation.
  • Making sure the bentonite is continually hydrated, where necessary, by periodically adding clean water to the bentonite that has been placed in the well.
  • Using a coating on the bentonite that retards swelling for several minutes to allow the bentonite pellets to drop through a shallow water column in the annular space.
  • Using slower expanding chips rather than pellets when dropping bentonite through a water column in the annular space.

In situations where there is too much water in the annular space to use a dry bentonite product, a grout mixture and a smaller tremie pipe should be used.

Grout Placement - Displacement Method

The displacement method involves calculating a volume of grout (sealant) material needed to fill the annular space.

Placing Grout Using the Displacement Method

To place grout using the displacement method:

  1. In many cases, a starter (or temporary) casing is placed into the hole to support the sides of the well. The sealant is typically installed into the drilled hole by a gravity method such as pouring the material from the ground surface. In this case the starter casing acts as a tremie pipe. In other cases, a tremie pipe is lowered into the open hole and the grout is placed into the open hole through a tremie pipe.

    Reminder - For further clarification of the definition of Tremie Pipe see Chapter 2: Definitions & Clarifications, Table 2-1 or the “Grout Placement – Pouring Bentonite Chips and Pellets from Surface” section in this chapter.

  2. A well casing with a plug located on the bottom of the casing is installed into the hole. The grout (sealant) is displaced by the casing and pushed up into the annular space.

    Reminder - Plugs should be made of material that is easily drilled through (e.g. wood or cement).

  3. If the sealant does not fill the entire annular space beside the well casing, then the sealant must be topped up using a tremie pipe to fill the entire annular space to the land surface.
    1. Where bentonite grout is used, and before further well construction proceeds, the bentonite should be allowed time to achieve full gel strength. Bentonite takes between 8 and 48 hours to achieve full gel strength.

    Best Management Practice – Topping Up Settled Bentonite Grout

    The bentonite grout should be topped up to the original level before drilling continues if there has been settling or subsidence in the annular space.

    1. Where cement grout is used, cement must be allowed to set according to manufacturer’s specifications, or 12 hours, whichever is longer. If there has been settling or subsidence in the annular space, the cement grout must be topped up to the original level before drilling continues.
  4. The plug is drilled out or removed from the bottom of the casing.

Reminder - The displacement method using a tremie pipe allows for the sealant to be continuously deposited into the hole. The casing with plug can then be installed into the well and meets the requirements of the Wells Regulation. The volume of sealant placed in the hole must be able to rise from the bottom of the annular space to the land surface.

Figure 7-18: Grout Displacement Method

See text below for description.

Figure 7-18 shows a cross-sectional diagram of the grout displacement method to place grout (sealant) into a well.

The diagram shows a vertical initial outer drill hole that extends into the subsurface. The subsurface consists of an upper layer of top soil underlain by a consolidated bedrock formation.

A suspended casing has been placed into the hole from above the ground surface to about three quarters of the depth of the hole. The bottom of the casing will eventually rest at the bottom of the initial drill hole. A drillable plug has been placed at the bottom of the casing. Centring guides have been placed on the upper and lower portion of the casing. The centring guides extend from the outside of the casing to the side of the hole. An annular space is located from the outside of the casing to the side of the hole. Suitable sealant (grout) has been placed into the hole with a tremie pipe (not shown) below the casing and around the casing from about half of the depth of the hole to the bottom of the hole.

  1. Grout measured and placed in hole through a tremie pipe.
  2. Well casing with bottom drillable plug and centralizers (centering guides) are placed into the well. The bottom of the well casing is placed at the bottom of the inital drill hole in the well.
  3. Well casing filled with water or pressure applied to hold casing in place until suitable sealant (grout) properly sets.

Reminder - This figure is not to scale, it is for illustrative purposes for this chapter only, and does not necessarily represent full compliance with other requirements found in the Wells Regulation.

Grout Placement - Double Plug Methodfootnote 8

This method is more common in the construction of oil and gas wells than test holes and dewatering wells. It involves calculating a volume of grout (sealant) material needed to fill the annular space. As this method involves installing the predetermined batch inside the well casing and pushing it into the annular space from below the well casing, care is needed to determine if the volume of grout (sealant) within the well casing exceeds the volume of the entire annular space.

Reminder - When determining the volume of grout needed, it is important to include an amount of grout that will leave 3 m to 4.6 m (10 ft to 15 ft) of grout (sealant) in the casing after the annular space has been filled.

Placing Grout Using the Double Plug Method

To place grout using the double plug method:

  1. A casing with a plug is installed in the hole. The casing is held above the bottom of the well. A pump and pipe are hooked onto the casing above the ground surface.

    Reminder - Plugs should be made of material that is easily drilled through (e.g., wood or cement).

  2. Grout (sealant) is pumped into the casing above the plug. In this case, the casing acts as the tremie pipe.
  3. A second plug is installed above the grout. The use of a plug helps ensure slurry and water separation, resulting in a proper grout seal at the lower end of the casing.
  4. Clean water or drilling fluid is then pumped into the casing causing the plugs and grout to move down the casing. As the plugs move down the casing, water or drilling fluid inside the casing is displaced. The process allows the lower plug to fall below the bottom of the casing and the grout moves up and into the annular space.
    1. Where bentonite grout is used, and before further well construction proceeds, the bentonite should be allowed time to achieve full gel strength. Bentonite takes between 8 and 48 hours to achieve full gel strength.

    Best Management Practice – Topping Up Settled Bentonite Grout

    The bentonite grout should be topped up to the original level before drilling continues if there has been settling or subsidence in the annular space.

    1. Where cement grout is used, cement must be allowed to set according to manufacturer’s specifications, or 12 hours, whichever is longer. If there has been settling or subsidence in the annular space, the cement grout must be topped up to the original level before drilling continues.
  5. The plugs are drilled out or removed from the bottom of the casing.

Reminder - Landing collars below the lower plug can be used to reduce the potential for over or under displacement of the grout (sealant). Wire lines attached to the upper plug can also be used to assist in accurately measuring depths when the plugs come together and reduce the risk of damage to the well casing.

Grout Placement - Annular Space For Driven Points

Definition - Construction by the use of a driven point means a method of well construction that uses a solid point or cone that is driven into the ground. This does not include a cutting shoe unless a solid point is installed on an inner rod. This method is not machinery specific.

For example, the type of machinery that can be used to drive the solid point or cone into the ground can include direct push technology, rotary, percussion, pneumatic hammers, sonic, non-powered manual methods, and cone penetration testing equipment.

The Wells Regulation - If a new test hole or dewatering well is constructed by the use of a driven point, the person constructing the well must ensure that any annular space created is filled to the ground surface using a material and a method approved in writing by the Director. An application must be made to the Director to obtain the written approval.

The request for an approved material and method to seal the annular space of a driven point test hole or dewatering well must be made and approved prior to constructing the new well. See the following sections in this chapter for details on the written consent process.

Reminder - The written approval requirement for a well that is constructed by the use of a driven point does not apply to a test hole or dewatering well that is scheduled to be abandoned not later than 180 days after completion of its structural stage.

Records of Site Condition Regulation - Starting on July 1, 2011, O. Reg. 153/04 prescribes that the provisions of the Ontario Water Resources Act and of Regulation 903 of the Revised Regulations of Ontario, 1990 (Wells) made under that Act, that would apply to a test hole but for section 1.1, and subsections 13 (2), 14.1 (2), 14.2 (3), 14.3 (2), 14.4 (4) and 14.5 (3) of that regulation, apply to a monitoring well installed for the purpose of,

  1. a phase one environmental site assessment; and
  2. a phase two environmental site assessment.
Implications for the Qualified Person

The qualified person shall ensure that phase one and phase two environmental site assessments (ESAs) are conducted in accordance with the requirements stated above.

Implications for Filling Annular Space Size for a New Test Hole Constructed by the Use of a Driven Point

With respect to annular space filling, the above requirement in O. Reg. 153/04 means that, if a new test hole is constructed by the use of a driven point, is scheduled to be abandoned not later than 180 days after the completion of its structural stage, and is to be used as a monitoring well in an ESA for a record of site condition, then:

  • the annular space filling exemptions for a test hole stated in this section do not apply, and
  • the requirement to ensure that the material and method used to fill any annular space are approved in writing by the Director.

Reminder - The above requirement in O. Reg. 153/04 also affects obligations such as casing material, well screen material and shallow works for monitoring wells. See Chapter 3: Exemptions: Wells, Activities & Experienced Professionals and Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well for further information.

Records of Site Condition Regulation - Please refer to O. Reg. 153/04 for RSC requirements.

Where Does The Person Constructing The New Well Have To Go To Seek A Written Consent From The Director?

If the person constructing a new well is required to seek the written consent of the Director to use an alternate method to fill the annular space of a well constructed by the use of a driven point, the person may contact the Wells Help Desk:

  • In writing to Wells Help Desk, Environmental Monitoring and Reporting Branch of the Ministry of the Environment and Climate Change, 125 Resources Road, Etobicoke ON M8P 3V6;
  • By fax at: 416-235-5960 or
  • By e–mail

For further information, the person constructing the well can contact the Wells Help Desk by telephone at 1-888-396-9355 (for Ontario residents only).

What Information Is Needed For A Written Consent?

The Ministry assesses each case individually and on its merits. As a minimum, applicant’s contacting the Ministry for a written approval should provide a written request that includes but is not limited to the following information:

  • The name of the individual(s)/entity that owns the test hole(s) or dewatering well(s)
  • The location of the test hole(s) or dewatering well(s)
  • The number of test hole(s) or dewatering well(s)
  • The purpose and use of the test hole(s) or dewatering well(s)
  • The type of casing and well screen that will be used
  • The type of sealant material and method being proposed to fill the annular space
  • The reason for the proposed sealant material and methods
  • If applicable, written certification by the manufacturer/installer/professional engineer that the material and method will properly fill the annular space
  • Details on how the person will verify that the placement of the sealant materials in the annular space is uniform and does not bridge
  • Details on any flowing well conditions and how the proposed material and method will prevent the vertical movement of groundwater in the annular space and near the well site
  • Details on any identified or expected contaminant or mineralized condition and how the proposed material and method will effectively seal the annular space to the ground surface
  • Other potential permits or approvals that are being applied for in relation to the construction or use of the well. For example, the need for a Permit To Take Water if the water from the well is being taken at a rate of more than 50,000 litres one any one day for well development purposes.

The person constructing the well may be required to retain a Professional Engineer or Professional Geoscientist who would have to prepare a scientific report showing the appropriate scientific rationale to support the application. The person constructing the well would have to submit the report along with the request for written approval to the Ministry for its consideration.

The Director has reviewed the following standards for test holes and dewatering wells:

  • ASTM D5092-04 – Standard Practice for Design and Installation of Ground Water Monitoring Wells; sections 6 to 8,
  • ASTM D6724-04 – Standard Guide for Selection and Installation of Direct-Push Ground Water Monitoring Wells, and
  • ASTM D6725-04 – Standard Practice for Direct-Push Installation of Pre-pack Screen Monitoring Wells in Unconsolidated Aquifers.

In many environments the Director will likely support a material and method for sealing the annular space that is consistent with these ASTM standards. As such, the person constructing the well is encouraged to review these ASTM standards and should indicate on the application, whether and how the standards listed above will be met.

How Does The Director’s Decision Process Work?

The request for written approval should be submitted to the Ministry along with any and all supporting documents such as a hydrogeological and/or a well design report. The person constructing the well and others should be cautioned that obtaining a written approval will not be an automatic process. The Ministry has to provide for the conservation, protection and management of Ontario’s waters and for their efficient and sustainable use, to promote Ontario’s long–term environmental, social and economic well–being.

The Ministry will review the request, supporting information and other information generated from internal and external parties with an interest in the application.

Based on the information, the Ministry will contact the person constructing the well in writing indicating the Director’s decision.

Tools For Annular Space & Sealing

Table 7-6 provides an example of the types of reference charts and tables that can be used to calculate volumes of holes and casing and determine the approximate amount of suitable sealant needed to fill the annular space.

Table 7-6: Calculating the Volume of the Casing and Hole
Diameter - Millimetres Diameter - Inches Volume - Cubic metres ⁄ metre Volume - Cubic feet ⁄ ft Volume - US gal/ft
51 2 0.002 0.022 0.161
64 2 ½ 0.003 0.032 0.241
76 3 0.005 0.054 0.402
89 3 ½ 0.006 0.065 0.483
102 4 0.008 0.086 0.643
114 4 ½ 0.010 0.108 0.804
127 5 0.013 0.140 1.046
127 5 0.013 0.140 1.046
140 5 ½ 0.015 0.161 1.206
152 6 0.018 0.194 1.448
165 6 ½ 0.021 0.226 1.689
178 7 0.025 0.269 2.011
191 7 ½ 0.029 0.312 2.332
200 7 ¾ 0.031 0.334 2.493
203 8 0.032 0.344 2.574
216 8 ½ 0.037 0.398 2.976
222 8 ¾ 0.039 0.420 3.137
229 9 0.041 0.441 3.297
241 9 ½ 0.046 0.495 3.700
248 9 ¾ 0.048 0.517 3.860
254 10 0.051 0.549 4.102
279 11 0.061 0.657 4.906
305 12 0.073 0.786 5.871
311 12 ¼ 0.076 0.818 6.112
324 12 ¾ 0.082 0.883 6.595
381 15 0.114 1.227 9.169
438 17 ¼ 0.151 1.625 12.144
445 17 ½ 0.155 1.668 12.466
457 18 0.164 1.765 13.190
508 20 0.203 2.185 16.327
610 24 0.292 3.143 23.485
635 25 0.317 3.412 25.495
762 30 0.456 4.908 36.675
914 36 0.657 7.072 52.840

Footnotes

  • footnote[*] Back to paragraph “Other wells” excludes dug wells, bored wells with concrete casing, jetted wells or wells that are constructed by the use of a driven point.
  • footnote[***] Back to paragraph Any annular space that may be created, other than the annular space surrounding a well screen or sampling port, must be sealed to prevent any movement of water, natural gas, contaminants or other material between subsurface formations or between subsurface formations and the ground surface by means of the annular space.
  • footnote[**] Back to paragraph The annular space depth requirement does not apply to situations where an inner casing is surrounded by a larger diameter permanent outer casing (see “Shallow Wells – Requirements and Exemptions” in this chapter and the minimum depth of a test hole and dewatering well with and without a well screen in the “Plainly Stated” section Chapter 6: Constructing the Hole, Casing & Covering the Test Hole or Dewatering Well).
  • footnote[1] Back to paragraph ASTM International, West Conshohocken, PA. ASTM website.
  • footnote[2] Back to paragraph Nielsen, David M. 2006. The Practical Handbook of Environmental Site Characterization and Ground-Water Monitoring, Second Edition. CRC/Taylor & Francis. Boca Raton, FL. Pp 755 to 769
  • footnote[3] Back to paragraph Halliburton. 2008. Quik Grout Data Sheet.
  • footnote[4] Back to paragraph Nielsen, David M. 1991. The Practical Handbook of Environmental Site Characterization and Ground-Water Monitoring, Second Edition. CRC/Taylor & Francis. Boca Raton, FL. P 665.
  • footnote[5] Back to paragraph The term “shear” is explained in the Glossary.
  • footnote[6] Back to paragraph Sterrett, Robert J. 2007. Groundwater and Wells-Third Edition. Johnson Screens/a Weatherford Company., New Brighton, MN. Pp453 to 454.
  • footnote[7] Back to paragraph Nielsen, David M. 1991. The Practical Handbook of Environmental Site Characterization and Ground-Water Monitoring, Second Edition. CRC/Taylor & Francis. Boca Raton, FL. P. 765
  • footnote[8] Back to paragraph Sterrett, Robert J. 2007. Groundwater and Wells – Third Edition. Johnson Screens/a Weatherford Company, New Brighton, MN. Pp. 461 to 462.